capture and manage the first flush runoff volume, as defined by the location’s frequent storm
event volume. Provide data for a year that is within the last five years. Points are awarded per
Table 1.
Table 1. Points for Mandatory Green Stormwater Infrastructure Capacity Performance Standards
| Percentile Storm Event | Points |
|---|---|
| 80th | 1 |
| 90th | 2 |
AND/OR
Option 2. Stormwater Management Policy and Planning (1 point)
Adopt and implement city-wide policy, plan, and/or ordinance that prioritizes green stormwater
infrastructure for new construction projects.
Include two of the following:
a. Require preparation of a stormwater management plan for significant development and
redevelopment activities.
b. Ensure support through a manual that establishes criteria, specifications, and recommended
practices when planning, designing, and constructing regulated sites and green stormwater
infrastructure within the city.
c. Minimum stormwater management control requirements and low-impact development
standards/practices to mimic predevelopment runoff conditions by managing the first 1.5 inches
of precipitation using infiltration, evapotranspiration, and rainwater harvesting. Captured rainwater
should be reused on-site to the maximum extent possible and allowable by local ordinance.
d. Requirement to implement integrated green stormwater infrastructure on city-owned buildings,
parking lots, parks, streets, and other facilities to demonstrate effectiveness and performance to
developers, citizens, and other relevant parties.
e. Provision of incentives for implementing on-site and off-site green stormwater infrastructure.
f. Dedicated funding for green stormwater infrastructure project implementation.
AND/OR
Option 3: Stormwater Management Monitoring Network (1 point)
81