| Building type | Climate zone | Col3 | Col4 | Col5 | Col6 | Col7 | Col8 | Col9 | Col10 | Col11 | Col12 | Col13 | Col14 | Col15 | Col16 | Col17 | Col18 | Col19 | Col20 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Building type | 0A | 0B | 1A | 1B | 2A | 2B | 3A | 3B | 3C | 4A | 4B | 4C | 5A | 5B | 5C | 6A | 6B | 7 | 8 |
| Hotel/motel | 0.65 | 0.63 | 0.64 | 0.63 | 0.62 | 0.61 | 0.62 | 0.63 | 0.62 | 0.59 | 0.60 | 0.60 | 0.57 | 0.58 | 0.59 | 0.56 | 0.58 | 0.56 | 0.56 |
| Office | 0.54 | 0.54 | 0.53 | 0.54 | 0.49 | 0.52 | 0.49 | 0.52 | 0.45 | 0.46 | 0.52 | 0.47 | 0.48 | 0.51 | 0.48 | 0.48 | 0.50 | 0.45 | 0.49 |
| Restaurant | 0.61 | 0.58 | 0.58 | 0.57 | 0.57 | 0.54 | 0.58 | 0.59 | 0.57 | 0.62 | 0.61 | 0.61 | 0.65 | 0.64 | 0.63 | 0.67 | 0.66 | 0.69 | 0.72 |
| Retail | 0.47 | 0.45 | 0.44 | 0.44 | 0.40 | 0.39 | 0.37 | 0.39 | 0.36 | 0.40 | 0.41 | 0.42 | 0.45 | 0.43 | 0.46 | 0.44 | 0.43 | 0.42 | 0.46 |
| School | 0.52 | 0.53 | 0.53 | 0.53 | 0.51 | 0.51 | 0.53 | 0.48 | 0.46 | 0.43 | 0.48 | 0.47 | 0.45 | 0.49 | 0.46 | 0.46 | 0.44 | 0.44 | 0.48 |
| Warehouse | 0.25 | 0.25 | 0.21 | 0.24 | 0.20 | 0.21 | 0.24 | 0.20 | 0.17 | 0.30 | 0.22 | 0.25 | 0.36 | 0.28 | 0.25 | 0.40 | 0.34 | 0.36 | 0.40 |
| All others | 0.58 | 0.56 | 0.56 | 0.56 | 0.50 | 0.47 | 0.49 | 0.48 | 0.48 | 0.49 | 0.49 | 0.50 | 0.51 | 0.50 | 0.55 | 0.52 | 0.52 | 0.52 | 0.55 |
REQUIREMENTS EXPLAINED
Widely referenced in building codes and regulations, ASHRAE Standard 90.1 determines the minimum energy efficiency required for prerequisite compliance.
Required ASHRAE Standard 90.1 Version
The required efficiency increases for project registrations beginning in 2028, stepping up from the ASHRAE Standard 90.1-2019 to the more stringent ASHRAE Standard 90.1-2022 . Compliance with ASHRAE 90.1-2022 achieves a net average site energy savings of 14% compared to ASHRAE 90.1-2019 when including savings for prescriptively required renewable energy.
Option 1. ASHRAE 90.1-2019
Only projects registered before January 1, 2028, can use ASHRAE 90.1-2019 . Projects must apply Addendum cr, which requires a building envelope backstop for projects documented using the Energy Cost Budget Method (ECB) or Appendix G, Performance Rating Method. All other ASHRAE 90.1-2019 addenda are optional.
Option 2. ASHRAE 90.1-2022
Projects registered after January 1, 2028, must use ASHRAE 90.1-2022 .
Projects registered before January 1, 2028, can use the 2022 version of the standard to earn points under EAc3: Enhanced Energy Efficiency .