Table 1. Key changes in ASHRAE 90.1-2022

SectionKey change
Additional efficiency
requirements

Section 11
For the prescriptive method of compliance, designers select from a list of 33
energy efficiency measures to satisfy the total required Energy Credits for a
given building type and climate zone, resulting in an average of 4% to 5%
savings.

These additional savings are also accounted for when determining the Energy
Cost Budget Method requirements and in the Building Performance Factors
referenced for the Appendix G Performance Rating Method.
On-Site Renewable
Energy

Section 10.5.1.1
On-site renewable energy is required for the prescriptive method, averaging
over 4% savings.

The Energy Cost Budget Method and Appendix G Performance Rating Method
factors in this prescriptive renewable contribution in determining compliance,
although other efficiency measures can make up the difference for project
designs without renewable energy.

Exceptions to On-Site Renewable Requirements

ASHRAE 90.1, Section 10.5.1.1 exempts buildings with inadequate access to
solar energy and small buildings with less than 10,000 sq. ft. (929 sq. m.) of
conditioned floor area for the three largest floors.

The following additional guidance applies to LEED projects:


Where regulatory limitations restrict maximum rooftop solar capacity,
use the lesser of the Section 10.5.1.1 criteria or the maximum capacity
or area stipulated by regulatory limitations.

Canadian provinces and U.S. eGRID regions aren’t required to have
on-site renewable. It’s also not required in other countries where
current annual electric grid emissions average less than 20 grams/kWh
CO2eq.

ASHRAE 90.1-2022, Addendum K provides additional alternatives for
projects to find off-site renewable energy meeting the prescriptive
requirements in lieu of the on-site renewable power.
Thermal Bridges

Section 5.5.5
A new prescriptive section addresses thermal bridging in the building envelope.
For projects utilizing Section 5.6, Building Envelope Trade-off Compliance
Path, the Energy Cost Budget Method, or the Appendix G, Performance Rating
Method, the proposed design model must account for thermal bridges that
don’t meet prescriptive requirements.

ASHRAE 90.1 Mandatory Provisions

All projects must meet applicable mandatory provisions from the referenced version of ASHRAE 90.1, found in Sections 5.4 (Building Envelope), 6.4 (HVAC), 7.4 (Service Water Heating), 8.4 (Power), 9.4 (Lighting), and 10.4 (Other Equipment).

U.S. Green Building Council LEED v5 Reference Guide for Building Design and Construction, April 2025 Launch Edition 213