proposed resolutions for outstanding items, copies of the final versions of the OPR and BOD, design review logs, copies of the approved submittals used for the FPTs, and copies of the completed FPTs.

Provide a preliminary Cx report for projects that finalize the LEED application before completing Cx. The Report must address all major envelope, MEP, renewable, and grid-interactive systems, confirm system installation, and indicate that Cx has commenced for all systems.

The CxP must provide the Final Cx Report to the owner once the Cx is complete.

Ongoing Cx Plan

An ongoing Cx Plan ensures systems remain operationally efficient throughout the building’s life. The plan should provide facility managers with procedures, blank FPTs, and a recommended schedule for ongoing Cx activities.

The ongoing Cx plan should address requirements for continuous documentation and updates. Building operations change over time, including retrofits or equipment replacement projects. Ensure the ongoing Cx plan reflects the most current information for the building.

KEY TASKS AND MILESTONES FOR COMMISSIONING

The Commissioning Provider is responsible for completing the following tasks to comply with EAp3: Fundamental Commissioning requirements :

  • Predesign (or immediately upon engagement of the CxP no later than the end of design development)

o Assist in the development of the OPR.

o Develop Cx Plan.

  • Design Phase

o Review Basis of Design (BOD).

o Develop or approve Cx specifications.

o Design document reviews (design drawings and specifications).

o Attend at least one coordination meeting.

o Assist in updating the OPR.

  • Construction Phase

o Perform focused submittal reviews for design deviations that impact the OPR.

o Perform field reviews.