| Phase | Task Descriptions | Fundamental ASHRAE 90.1-2019 | Enhanced ASHRAE 202-2018 | Minimum Requirements as listed |
|---|---|---|---|---|
| scheduling of design and submittal reviews. | ||||
| Develop Cx Plan | Section 4.2.5.2.1 Section 4.2.5.2.2 | Section 7.2, 7.3 | Fundamental and Enhanced: Development of Cx Plan. Enhanced: Update Cx plan at least once per phase (DD, CD, Construction). | |
| Design Phase | Review Basis of Design (BOD) | Required by LEED | Section 8.2, 8.3 | Enhanced: Review BOD for compliance with OPR. |
| Design Phase | Update Cx Plan | Not Required | Section 7.2, 7.3 | Enhanced: Update Cx plan at least once per phase (DD, CD, Construction). |
| Design Phase | Develop Cx Specification | Section 4.2.5.1.1, 4.2.5.2.1, 6.9.2 | Section 9.2, 9.3 | |
| Design Phase | Design Document Reviews (Design Drawings and Specifications) | Section 4.2.5.2, 4.2.5.2.2 | Section 10.2, 10.3 | Full Drawing and Specification Review for systems to be commissioned. Fundamental and Enhanced: detail compliance with the OPR and provisions in respective standards. Each design review to include issues log for tracking/resolution of issues. Enhanced: Back- check review to confirm if recommendations |
U.S. Green Building Council LEED v5 Reference Guide for Building Design and Construction, April 2025 Launch Edition 238