| Phase | Task Descriptions | Fundamental ASHRAE 90.1-2019 | Enhanced ASHRAE 202-2018 | Minimum Requirements as listed |
|---|---|---|---|---|
| Submittal Review | Required by LEED | Section 11.2, 11.3 | Fundamental: Review submittals or substitutions for design deviations impacting the OPR. Enhanced: Thorough review of relevant building system submissions for compliance with the Design Documents and OPR. | |
| Schedule | Required relative to other tasks | Section 7.2.3.d | Fundamental: Ensure Cx requirements/ milestones are included in the project construction schedule. Enhanced: Detailed description of Cx activities and a schedule of activities. Schedule is included in the Cx plan. | |
| Field Reviews | Section 4.2.5.1 | Section 12.2.6 | Fundamental: Minimum of one site visit to verify Cx readiness Enhanced: Minimum of one site visit to review contractor completed construction checklists. A checklist for each major system type should be reviewed during the site visit. | |
| Testing (Review/witness performance testing) | Section 4.2.5.2 | Section 12.2.6 | Fundamental and Enhanced: Minimum of one site visit to witness execution of functional- |
U.S. Green Building Council LEED v5 Reference Guide for Building Design and Construction, April 2025 Launch Edition 240