PhaseTask DescriptionsFundamental
ASHRAE
90.1-2019
Enhanced
ASHRAE
202-2018
Minimum
Requirements as
listed
Submittal ReviewRequired by
LEED
Section 11.2,
11.3
Fundamental:
Review submittals
or substitutions for
design deviations
impacting the OPR.

Enhanced:
Thorough review of
relevant building
system submissions
for compliance with
the Design
Documents and
OPR.
ScheduleRequired
relative to
other tasks
Section 7.2.3.dFundamental:
Ensure Cx
requirements/
milestones are
included in the
project construction
schedule.

Enhanced:
Detailed description
of Cx activities and
a schedule of
activities. Schedule
is included in the Cx
plan.
Field ReviewsSection
4.2.5.1
Section 12.2.6Fundamental:
Minimum of one site
visit to verify Cx
readiness

Enhanced:
Minimum of one site
visit to review
contractor
completed
construction
checklists. A
checklist for each
major system type
should be reviewed
during the site visit.
Testing
(Review/witness
performance
testing)
Section
4.2.5.2
Section 12.2.6Fundamental and
Enhanced:
Minimum of one site
visit to witness
execution of
functional-

U.S. Green Building Council LEED v5 Reference Guide for Building Design and Construction, April 2025 Launch Edition 240