| Phase | Task Descriptions | Fundamental ASHRAE 90.1-2019 | Enhanced ASHRAE 202-2018 | Minimum Requirements as listed |
|---|---|---|---|---|
| performance testing, per the scope of the project. | ||||
| Meetings | Required by LEED | Required by LEED | Fundamental and Enhanced: Milestone meetings at 50% and 100% | |
| QA/QC Documentation (Checklist and Tests) | Required by LEED | Section 12.2.2a, 12.2.6.c | Fundamental: Sample review of completed contractor documentation (i.e., 10%) Enhanced: Additional reviews of completed contractor documentation (i.e., 25%) | |
| Track identified issues to resolution (Issues/Resolution Log) | 4.2.5.1, 4.2.5.2 | Section 13.2, 13.3 | Fundamental: Include Issues and Resolution (I/R) Log in the preliminary Cx r Report. Enhanced: Maintain a formal I/R log throughout the project until the owner resolves or accepts all issues. The final I/R log, with all items closed, is included in the final Cx rReport. | |
| Systems Manual | Not Required | Section 14.2, 14.3 | Enhanced: Compile the Systems Manual, which includes all information needed to understand, operate and maintain the building’s systems and assemblies. |
U.S. Green Building Council LEED v5 Reference Guide for Building Design and Construction, April 2025 Launch Edition 241