| Phase | Task Descriptions | Fundamental ASHRAE 90.1-2019 | Enhanced ASTM E2947- 2021 | Minimum Requirements as listed |
|---|---|---|---|---|
| prior to end of Design Phase. | ||||
| Construction Phase | Pre-Construction Kick-off Meeting | Not Required | Section 9.2.1 | Enhanced: BECxA to lead meeting, prepare agenda to minimally include discussion on roles/responsibilitie s, BECx plan and spec overview, schedule, summary of mock-up, site reviews and testing. |
| Construction Phase | Review Submittals/Substitut ions | Required by LEED | Section 9.2.2 | Fundamental: Review submittals/substituti ons for design deviations that impact the OPR. Enhanced: Thorough review of relevant building envelope submissions for compliance with the Design Documents and OPR. |
| Construction Phase | Schedule | Required relative to other tasks | Section 9.2.2.3 | Fundamental: Ensure BECx requirements and milestones are in the project Construction Schedule. Enhanced: Review and comment on Construction Schedules as required. |
| Construction Phase | Mock-ups | Not Required | Section 9.3.3 | Enhanced: Attend mock-up reviews (laboratory, factory, Performance mock- ups (PMU), in place mock-ups) as applicable. |