| Phase | Task Descriptions | Fundamental ASHRAE 90.1-2019 | Enhanced ASTM E2947- 2021 | Minimum Requirements as listed |
|---|---|---|---|---|
| well as report summarizing BECx activities to end of Construction Phase, Including OPR, BECx Plan and reports. | ||||
| Occupancy/Operat ions Phase | Review Building Envelope Training Program | 4.5.2.2.2.c.5 | Section 10.2 | Review that training plan has been implemented. |
| Occupancy/Operat ions Phase | Post-Occupancy Review | Not Required | Section 10.3 | Enhanced: Conduct minimum of one in-person post occupancy site visit with Facility Maintenance staff (or similar) before the end of envelope warranty period. |
| Occupancy/Operat ions Phase | Final BECx Report | Section 4.2.5.2.2.d | Section 10.1 | Full report summarizing BECx activities, including Occupancy Phase activities. |
| Occupancy/Operat ions Phase | On-going BECx Plan | Not Required | Section 10.4 | Enhanced: Contribute to development of Preventative Maintenance Plan for Building Envelope (i.e., On- Going BECx Plan) for owner. |
Core and Shell
For LEED BD+C: Core and Shell projects, complete commissioning for systems within the core and shell scope of work. Follow all BD+C: New Construction requirements with the following guidance.
SCOPE OF WORK
The commissioning scope of work for a Core and Shell project varies depending on the energy and water-using systems included in the design. For example, a project may consist of base building systems, like air-source heat pumps and central air handling units. Alternatively, the developer may limit the scope of work and provide a cold shell with no central HVAC equipment and minimal levels of lighting. Per the project scope, the CxP must verify and test systems.