DESIGN REVIEW FOR CORE AND SHELL PROJECTS
During the design reviews, include review comments on LEED BD+C: Core and Shell systems and how any incomplete system can meet ASHRAE Standard 90.1 requirements for tenant fitouts. This includes both energy efficiency measures and tenant metering requirements.
FINAL COMMISSIONING REPORT
Along with the required elements listed in the Final Commissioning Report section above, identify and defer any tests until base building systems connect with future tenant equipment (e.g., a central VAV air handling unit with controls testing that must be deferred until after installing tenant VAV terminal equipment).
TENANT GUIDELINES FOR COMMISSIONING
IPp4: Tenant Guidelines allow owners to inform all tenants of the building’s sustainable design and construction features. Project teams are encouraged to include a section on commissioning addressing any interconnection between base building and tenant-installed systems.
DOCUMENTATION
| Project types | Options | Documentation |
|---|---|---|
| All | All | If the report is a draft, include a plan for the completion of commissioning and training, including climatic and other conditions required for performance of any deferred tests. |
| All | All | Confirmation of compliance with_ANSI/ASHRAE/IES Standard 90.1_ commissioning requirements for building systems, controls, and the building envelope (Section 4.2.5.2 exceptions shall not apply). |
| All | All | Confirmation of design phase meeting. |
| All | All | Provide Commissioning Plan and sample FPT Test scripts (one sample per discipline). |
| All | All | Owner’s Project Requirements and BOD |
| All | All | Identification of Commissioning Provider including key personnel (CxP) and Verification and Testing (V&T) providers (as applicable). |
| All | All | Qualifications of CxP and V&T providers. |
| All | All | Ongoing Cx Plan (post-occupancy). |
| All | All | Confirmation of construction phase milestone meetings at 50% and 100% completion. |
| All | All | Confirmation that submittals were reviewed and at least 10% of the contractor’s documents were QA/QC’d |
U.S. Green Building Council LEED v5 Reference Guide for Building Design and Construction, April 2025 Launch Edition 248