Combined Heat and Power To limit undue credit for site-recovered energy from Combined Heat and Power (CHP) with onsite combustion emissions, projects must model CHP systems using one of the following methods instead of ASHRAE 90.1 G2.4.2.1:

  • CHP in baseline and proposed . Model CHP systems including all fuel inputs and associated site-recovered energy identically in the baseline design and the proposed design.

  • Purchased electricity in baseline and proposed . Model purchased electricity instead of the on-site electricity generation. Either credit site-recovered energy from the CHP towards the thermal loads for the baseline and proposed design identically or ignore the site-recovered energy contribution in the baseline and proposed design).

  • CHP in proposed; purchased electricity in baseline . Model CHP systems including all fuel inputs and associated site-recovered energy in the proposed design. Model the baseline design per ASHRAE 90.1 with purchased electricity and with no credit for siterecovered energy.

DOCUMENTATION
Project
types
OptionsPathsDocumentation
New
Construction
and
Core and
Shell
Option 1Path 1: Case 1
and 2
Demonstrate compliance with_EAp2: Minimum Energy_
Efficiency.
New
Construction
and
Core and
Shell
Option 1Path 1: Case 1
and 2
List options showing prescriptive compliance with
ASHRAE 90.1 2019.
New
Construction
and
Core and
Shell
Option 1Path 2: Case 1IT department policies for plug load controls.
New
Construction
and
Core and
Shell
Option 1Path 2: Case 1Evidence of a plug load dashboard accessible to all
regular occupants of the building (specifications,
photos, screenshots, etc.)
New
Construction
and
Core and
Shell
Option 1Path 2: Case 2
Provide documentation demonstrating the_ISO 25745_
rating for people conveyance equipment (as
applicable).
New
Construction
and
Core and
Shell
Option 1Path 2: Case 2
Provide the design ELC calculation following methods
in Informative Appendix C, and calculation for the
percentage of reduction from_ASHRAE 90.4-2022_
maximum design electrical loss (as applicable).
New
Construction
and
Core and
Shell
Option 1Path 2: Case 2
Provide refrigeration equipment cut-sheets (as
applicable).
New
Construction
and
Core and
Shell
Option 1Path 2: Case 2
Provide refrigerated warehouse design documents to
verify compliance with_California Title 24-2022 Section_
120.6 (as applicable).
New
Construction
and
Core and
Shell
Option 1Path 2: Case 2
Provide documentation for the Baggage Handling
Equipment Individual Carrier System, such as
specifications or cut sheets, to verify the installation of
variable frequency drives (as applicable).