Envelope commissioning must address any potential impact of the roof mounts on the building enclosure integrity, including thermal bridging and/or moisture intrusion.

Interconnection pathways Dedicated areas must be designed for future inverters and metering equipment, and pathways reserved for conduit routing. These interconnection pathways must specifically address anticipated tenant design configurations. For example, for distributed net-metering of each tenant’s electricity, the design should accommodate conduit pathways to the projected location for each tenant electrical panel and should reserve nearby space for inverters and other equipment. For projects where solar thermal hydronic systems may be installed, the design should address pathways for routing of plumbing.

Electrical service Sufficient electrical space must be permanently reserved and marked for future solar electric use within the main electrical service panel.

LEED Platinum Requirements

To achieve LEED Platinum, projects must supply 100% of energy usage from any combination of Tier 1, Tier 2, and/or Tier 3 renewable energy:

  • New construction . 100% of total annual site energy usage

  • Core and Shell . 100% of total annual base building site energy usage

Refer to the Project Priorities Library for regional compliance alternatives.

DOCUMENTATION
Project
types
OptionsPathsDocumentation
New
Construction
and
Core and
Shell
AllAllFor third-party-owned systems, provide a purchase letter
or contract of commitment showing renewable energy for
targeted point threshold, including confirmation of
renewable attribute ownership, quantity of renewable
energy, type of renewable energy, country or region,
duration of contract, and commercial operations date
(COD).
New
Construction
and
Core and
Shell
AllAllConfirmation of renewable attribute ownership by building
owner.
New
Construction
and
Core and
Shell
AllAllFor shared RE attributes, provide confirmation of
allocation of attributes to the project. Documentation from
owner’s representative confirming the capacity/generation
that is allocated to the project building and confirming that
this capacity/generation will double count toward any
other LEED projects, only for projects that share on-site

U.S. Green Building Council LEED v5 Reference Guide for Building Design and Construction, April 2025 Launch Edition 351