Option 2. Monitoring-based Commissioning
Meet the same requirements as BD+C: New Construction Option 2, plus:
For Core and Shell projects, the base building EIS must have expansion capability, to ensure all data identified in EAp4: Energy Metering and Reporting is accessible through the EIS. This includes metering requirements for future tenants.
Tenant requirements If the project anticipates future tenants will lease space that is greater than 10,000 sq. ft. (929 sq. m.), install submeters for compliance with EAp2: Minimum Energy Efficiency . The base building EIS must include a tenant portal, where tenants can access reports, including visual representations of the energy consumption. At minimum, tenants must have access to the base building data for shared systems that serve the tenant space, and the electricity energy use associated with their space.
DOCUMENTATION
| Project types | Options | Paths | Documentation |
|---|---|---|---|
| New Construction and Core and Shell | All | All | Final (or Draft) Commissioning Report. If the report is a draft, include a plan for the completion of commissioning and training, including climatic and other conditions required for performance of any deferred tests. |
| New Construction and Core and Shell | Option 1 | Path 1 and/or Path 2 | Confirmation of compliance with_ANSI/ASHRAE/IES_ Standard 202-2024 and/or_ASTM E2947-21a Standard_ Guide for Building Enclosure Commissioning, except Section 7.2.4 and 7.4.3 (As applicable) |
| New Construction and Core and Shell | Option 1 | Path 1 and/or Path 2 | Confirmation of design phase/milestone meetings |
| New Construction and Core and Shell | Option 1 | Path 1 and/or Path 2 | Provide Commissioning Plan and sample FPT Test scripts (1 sample per discipline) |
| New Construction and Core and Shell | Option 1 | Path 1 and/or Path 2 | Owner’s Project Requirements and BOD |
| New Construction and Core and Shell | Option 1 | Path 1 and/or Path 2 | Identification of Commissioning Provider including key personnel (CxP) and Verification and Testing (V&T) providers (as applicable) |
| New Construction and Core and Shell | Option 1 | Path 1 and/or Path 2 | Qualifications of CxP and V&T providers |
| New Construction and Core and Shell | Option 1 | Path 1 and/or Path 2 | Confirmation that submittals were reviewed and at least 25% of the contractors’ documents were QA/QC’d |
| New Construction and Core and Shell | Option 1 | Path 1. Enhanced Cx for MEP Systems | Provide evidence, such as contract or other documentation, confirming the involvement of CxP during predesign or very early in the design phase |
| New Construction and Core and Shell | Option 1 | Path 2. Enhanced Cx for building Enclosure | Field report or completed test that proves building air leakage testing, water penetration testing, infrared imaging was completed |
U.S. Green Building Council LEED v5 Reference Guide for Building Design and Construction, April 2025 Launch Edition 367