CreditEnhanced Commissioning (continued)
  • Added Core + Shell specific options and paths including Enhanced Commissioning for Building Enclosure or Enhanced Commissioning for Building Enclosure and MEP systems, Monitoring-Based Commissioning Process and Communications or Energy Information Systems.
  • Removed separate data center requirements for enhanced commissioning.
CreditOptimize Energy Performance
  • Credit renamed to: EAc Enhanced Energy Efficiency.
  • Several points reallocated to LEED v5 EAc Electrification and EAc Reduced Peak Thermal Loads credits.
  • Option 1: reduction of regulated loads per version of 90.1 used in EAp Minimum Energy Efficiency AND/OR reduction of unregulated loads.
  • Option 2: whole building simulation to show improvement over 90.1 version used for EAp Minimum Energy Efficiency; option to include on-site renewable energy production.
CreditAdvanced Energy Metering
  • Credit removed and partially incorporated into: EAc Grid Interactive credit, Option 3.
CreditDemand Response
  • Credit renamed to: EAc Grid Interactive.
  • Can use a combination of options 1 through 4.
  • Option 1: Energy Storage (Added).
  • Option 2: Demand Response Program.
  • Option 3: Automated Demand Side Management via System or BAS.
  • Option 4: Power Resilience for critical systems (Added).
CreditRenewable Energy Production
  • Credit renamed to: EAc Renewable Energy.
  • New calculation method based on Tier 1, Tier 2, and Tier 3 renewables.
  • Projects may combine Tier 1, Tier 2, and Tier 3 renewable options to achieve points.
  • Still subject to contract length, vintage, location, and EAC/REC ownership requirements.
  • Core + Shell projects have the option to incorporate renewable ready design.
CreditEnhanced Refrigerant Management
  • Option 1: no or low GWP refrigerant.
  • Option 2: design, installation, and operational measures to reduce refrigerant leakage.
  • Option 3: (food retailers only) Green Chill Certification.
CreditGreen Power and Carbon Offsets
  • Credit removed and incorporated into EAc Renewable Energy.
CreditElectrification
  • New credit.
CreditReduce Peak Thermal Loads
  • New credit.
CreditGrid Interactive
  • New credit. Incorporates LEED v4 EAc Demand Response credit and portions of EAc Advanced Energy Metering credit.