Points documented for Tier 1, Tier 2, and/or Tier 3 renewable energy may be added together up to a maximum of 4 points.

Table 2. Points for Renewable Energy Procurement

PointsTier 1Col3Col4Tier 2Tier 3
PointsMinimum Rated
Capacity*
ORAnnual Electric
Energy Use (%)
Annual Electric
Energy Use (%)
Annual Electric
Energy Use (%)
1
A × 1 W/sq. ft.
(A × 10.8 W/sq. m.)
OR
5%

20%

50%
2
A × 2 W/sq. ft.
(A × 22.5 W/sq. m.)
OR10%40%100%
3



20%60%
430%80%

*A = Sum of gross floor area of all floors up to the three largest floors.

RENEWABLE ENERGY CLASSIFICATIONS

Tier 1. On-Site Renewable Energy Generation or Social Impact Project

The renewable generation equipment may be located:

  • On the project site

  • On the campus on which a project is located

  • On the site of a social impact project, provided that the renewable power system is provided, installed, and commissioned at no cost to the social impact entity; that the ownership of the renewable power system is transferred to the social impact entity; and that the rights to the power provided be given to the social impact entity

Tier 2. New off-site Renewable Electricity

Off-site renewable electricity produced by new generation asset(s):

  • Off-site renewable electricity produced by new generation asset(s) initially contracted no more than five years after the asset’s commercial operations date

Tier 3. Off-site Renewable Energy

  • Off-site renewable electricity that is Green-e® Energy certified or equivalent

  • Renewable fuels that are Green-e Renewable Fuels certified or equivalent

U.S. Green Building Council LEED v5 Reference Guide for Operations and Maintenance, November 2025 Edition 39