  • Develop a list of retro-commissioning measures (RCMs), identifying all problems to be remedied and the responsible party who will address each measure, timeline and estimated cost, if applicable.

    • Develop a rough estimate of predicted energy savings due to RCx.

Implementation phase

  • Complete all RCMs except for RCMs that entail significant capital expense, as determined by the owner.

Verification phase

  • Verify that RCMs are performing as intended.

Handoff phase

  • Finalize the RCx report. Update the current facilities requirements (CFRs) and operations and maintenance (O+M) plan and train the building operator.

OR

Option 2. Monitoring-Based Commissioning (1–2 points)

PATH 1. BASIC MBCX (1 POINT)

Implement a monitoring-based commissioning (MBCx) process during the 12-month reporting period with a plan for continuing MBCx for a minimum of three years. Include all of the following:

MBCx plan Develop an MBCx plan and include it in the CFR and O+M plan. The MBCx plan must describe:

  • Roles and responsibilities

  • Training of facilities staff

  • Software technology description, including frequency and duration of trend monitoring

  • Action plan for identifying, prioritizing, and correcting operational errors, and for verifying the correction of operational errors

  • Review and report criteria; at least annually, provide a summary report of trends, benchmarks, faults, energy savings opportunities, corrective actions taken, and planned actions to facilities management and/or building ownership

Energy information systems Have in place a remotely accessible platform with software functionality to perform smart analytics and visually present energy consumption and electricity demand data. Tenant energy use and electricity demand may be excluded. Include the following functionality:

U.S. Green Building Council LEED v5 Reference Guide for Operations and Maintenance, November 2025 Edition 55