Water Efficiency Prerequisite
MINIMUM WATER EFFICIENCY
WEp1
REQUIRED
INTENT
To reduce potable water consumption and the associated energy consumption and carbon emissions required to treat and distribute water and preserve potable water resources through an efficiency-first approach.
REQUIREMENTS
| Achievement pathways | Points |
|---|---|
Commercial Interiors | N/A |
Minimum Fixture and Fittings Efficiency | |
Option 1. Prescriptive Path — Maximum Flush and Flow Rates | Option 1. Prescriptive Path — Maximum Flush and Flow Rates |
OR | OR |
Option 2. Performance Path — Calculated Reduction | Option 2. Performance Path — Calculated Reduction |
AND | AND |
Minimum Equipment Water Efficiency | Minimum Equipment Water Efficiency |
Meet all minimum water efficiency requirements outlined below, as applicable to the project scope.
Minimum Fixture and Fittings Efficiency
Meet the minimum water efficiency requirements for fixtures and fittings outlined below.
Projects located where standard supply pressure is different than the LEED baseline supply pressure may calculate the water consumption of flow fixtures and fittings at the local standard supply pressure.
OPTION 1. PRESCRIPTIVE PATH — MAXIMUM FLUSH AND FLOW RATES
For all new and existing fixtures and fittings within the tenant space, do not exceed the maximum flush and flow rates listed in Table 1.