PATH 3. PROCESS WATER USE

Projects pursuing this path must demonstrate that process water exceeds 10% of the total building-regulated water use, excluding cooling water.

Using alternative water sources, such as captured condensate from air handling units, reduces reliance on fresh water for process systems. Diversifying the water sources on a project site also builds resilience in buildings. This allows projects to divert freshwater for human consumption instead of processes during a water crisis.

When selecting the alternative water source, ensure that the quality of the water is sufficient for its intended use and that the local authority having jurisdiction (AHJ) allows that alternative water source, per local codes and standards.

DOCUMENTATION
Project
types
OptionsPathsDocumentation
AllOption 1.
Whole Project
Water Use
All
LEED v5 Whole Project Water Use calculator.
AllOption 1.
Whole Project
Water Use
All
Contract documents and manufacturer information to
support the baseline and proposed water use values in
the calculator.
AllOption 2.
Fixtures and
Fittings
All

LEED v5 Fixture and Fittings Efficiency calculator,
documenting the fixtures/fittings within and outside of
the tenant space. If there are fixtures both within and
outside the tenant space, this will be a separate,
additional calculator from that submitted for the
prerequisite.
AllOption 2.
Fixtures and
Fittings
All

Evidence of any plumbing fixtures and fittings used by
the project occupants outside of the tenant space,
including flush/flow rates (recommended: product
information from the manufacturer, photographs with
date/time/location stamp, and/or as-built documents).
AllOption 3.
Appliance and
Process Water

All

Contract document(s) specifying the project’s newly
installed commercial washing machines, commercial
food waste disposers, commercial laboratory and
medical equipment, and/or municipal steam systems
and process water equipment, as applicable, including
performance specifications.
AllOption 4.
Optimize
Process Water
Use
Path 1. Limit
Cooling Tower
Cycles

Results from the potable water analysis for cooling
towers and evaporative condensers. Include the
concentration levels for all five parameters listed in
Table 8 of the rating system.

AllOption 4.
Optimize
Process Water
Use
Path 2. Optimize
Water Use for
Cooling


Equipment schedule indicating cooling tower type.
AllOption 4.
Optimize
Process Water
Use
Path 2. Optimize
Water Use for
Cooling
Calculation showing the baseline process water use.
AllOption 4.
Optimize
Process Water
Use
Path 2. Optimize
Water Use for
Cooling
Calculation showing the design process water use,
including any alternative water savings.

U.S. Green Building Council LEED v5 Reference Guide for Interior Design and Construction, April 2025 Launch Edition 93