| Col1 | Col2 | Col3 | Col4 | activities. Schedule is included in the Cx plan. |
|---|---|---|---|---|
| Field reviews | Section 4.2.5.1 | Section 12.2.6 | Fundamental: Minimum of one site visit to verify Cx readiness. Enhanced: Minimum of one site visit to review contractor completed construction checklists. A checklist for each major system type should be reviewed during the site visit. | |
| Testing (review/witness performance testing) | Section 4.2.5.2 | Section 12.2.6 | Fundamental and Enhanced: Minimum of one site visit to witness execution of functional- performance testing, per the scope of the project. | |
| Meetings | Required by LEED | Required by LEED | Fundamental: At least one meeting to discuss review comments and commissioning Enhanced: At least two milestone meetings (i.e., 25%, 50%, 75%, and 100% of schedule). | |
| QA/QC Documentation (checklist and tests) | Required by LEED | Section 12.2.2a, 12.2.6.c | Fundamental: Sample review of completed contractor documentation (i.e., 10%) Enhanced: Additional reviews of completed contractor documentation (i.e., 25%) | |
| Track Identified Issues to Resolution (Issues / Resolution Log) | 4.2.5.1, 4.2.5.2 | Section 13.2, 13.3 | Fundamental: Include (I/R) log in the Preliminary Cx Report Enhanced: A formal I/R log shall be maintained throughout the project until all issues are resolved or accepted by the owner. Include the final I/R log, with all items closed, in the final Cx report. | |
Systems Manual | Not Required | Section 14.2, 14.3 | Enhanced: Compile the systems manual, which includes all information needed to understand, operate, and maintain the building’s systems and assemblies. |
U.S. Green Building Council LEED v5 Reference Guide for Interior Design and Construction, April 2025 Launch Edition 126