855773520-LEED-v5-ID-C-Reference-Guide-Launch-Edition-1 - Page 139
Extracted Content
DOCUMENTATION
| Project types | Options | Paths | Documentation |
|---|---|---|---|
| All | All | All | Final (or draft) commissioning report. If the report is a draft, include a plan for the completion of commissioning and training, including climatic and other conditions required for performance of any deferred tests. |
| All | All | All | Identification of CxP including key personnel and V&T providers (as applicable). |
| All | All | All | Qualifications of CxP and V&T providers. |
| All | All | All | Confirmation that BOD/OPR were reviewed by CxP. |
| All | All | All | Confirmation of design phase/milestone meetings. |
| All | All | All | Confirmation that submittals were reviewed and at least 10% were QA/QC’d. |
| All | All | All | Confirmation of compliance with_ANSI/ASHRAE/IES_ _Standard 90.1_commissioning requirements for building systems, controls, and the building envelope (Section 4.2.5.2 exceptions shall not apply) as applicable to the scope of work. |
REFERENCED STANDARDS
-
ANSI/ASHRAE/IES Standard 90.1 commissioning requirements for building systems, controls, and the building envelope, with the following additional provisions
- The referenced version with errata shall be:
o 2019 for projects registered prior to January 1, 2028,
(store.accuristech.com/ashrae/standards/ashrae-90-1-2019-i- p?product_id=2088527)
o 2022 for projects registered on or after January 1, 2028,
(store.accuristech.com/ashrae/standards/ashrae-90-1-2022-i- p?product_id=2522082)
U.S. Green Building Council LEED v5 Reference Guide for Interior Design and Construction, April 2025 Launch Edition 128