  • SWH equipment in nonresidential spaces complying with the point-of-use water heater criteria in ASHRAE 90.1-2022, Section 11.5.2.3.3, W05, without exceptions

OR

Option 2. No On-Site Combustion Except at Low Temperatures—Base Building and Tenant Systems (1–5 points)

Pursue any combination of the following paths for a maximum of 4 points:

PATH 1. SPACE HEATING (2 POINTS)

Design space heating to be capable of operating without on-site combustion except at low temperatures. Projects in climate zones 3 and above must have a weighted average space heating equipment efficiency of at least 1.8 COP for initial build-out construction or at least 1.2 COP for alterations.

The following equipment may be excluded from the COP determination:

  • Supplemental heating equipment designed only for operation at low temperatures

AND/OR

PATH 2. SWH (1 POINT)

Design SWH systems to be capable of operating without on-site combustion except at low temperatures. Projects with total SWH capacity exceeding 34,000 Btu/hr (10 kW) must have a weighted average service hot water equipment efficiency of at least 1.8 COP for initial build-out construction or at least 1.2 COP for alterations.

The following equipment may be excluded from the COP determination:

  • SWH equipment in nonresidential spaces complying with the point-of-use water heater criteria in ASHRAE 90.1-2022, Section 11.5.2.3.3, W05, without exceptions

  • Supplemental heating equipment designed only for operation at low temperatures

AND/OR

PATH 3. COOKING AND OTHER PROCESS LOADS (1–2 POINTS)

Design cooking, laundry, process equipment, and on-site power generation except emergency support systems to be capable of operating without on-site combustion.

Not in scope (1 point)

  • Cooking, laundry, or process heating systems are not in project scope of work.

U.S. Green Building Council LEED v5 Reference Guide for Interior Design and Construction, April 2025 Launch Edition 143