855773520-LEED-v5-ID-C-Reference-Guide-Launch-Edition-1 - Page 178

Extracted Content

Table 7. ASHRAE 90.1-2019 — Equivalent BPFs for a future source energy metric

Building typeClimate zoneCol3Col4Col5Col6Col7Col8Col9Col10Col11Col12Col13Col14Col15Col16Col17Col18Col19Col20
**Building type **
0A
0B
1A
1B
2A
2B
3A
3B
3C
4A
4B
4C
5A
5B
5C
6A
6B
7
8
Multifamily0.74
0.69
0.73
0.70
0.73
0.70
0.71
0.70
0.63
0.70
0.71
0.69
0.68
0.70
0.70
0.68
0.68
0.68
0.74

Healthcare/hospital
0.72
0.72
0.73
0.73
0.74
0.71
0.72
0.74
0.71
0.72
0.73
0.71
0.74
0.73
0.80
0.73
0.77
0.78
0.79

Hotel/motel
0.72
0.71
0.72
0.71
0.71
0.70
0.71
0.73
0.72
0.71
0.73
0.73
0.71
0.73
0.74
0.70
0.72
0.70
0.70

Office
0.62
0.63
0.61
0.62
0.58
0.60
0.57
0.62
0.55
0.55
0.61
0.57
0.58
0.61
0.59
0.58
0.60
0.54
0.58

Restaurant
0.65
0.62
0.63
0.61
0.62
0.58
0.63
0.63
0.63
0.67
0.66
0.66
0.70
0.70
0.68
0.73
0.72
0.74
0.77

Retail
0.57
0.54
0.53
0.53
0.48
0.47
0.47
0.47
0.47
0.52
0.50
0.56
0.57
0.53
0.59
0.58
0.56
0.53
0.60

School
0.57
0.57
0.58
0.57
0.55
0.54
0.57
0.51
0.49
0.48
0.51
0.52
0.51
0.53
0.51
0.53
0.50
0.51
0.58

Warehouse
0.28
0.30
0.24
0.27
0.23
0.24
0.27
0.23
0.20
0.33
0.26
0.28
0.40
0.32
0.29
0.44
0.38
0.40
0.44

All others
0.650.620.640.620.570.540.570.560.580.590.570.600.600.590.650.620.620.610.64
REQUIREMENTS EXPLAINED

This credit rewards increased energy efficiency addressing regulated and unregulated systems in the project scope, and improved base building performance . To limit documentation level of effort, use the same ASHRAE 90.1 compliance method for prerequisite and credit compliance: either the prescriptive method or Appendix G PRM.

Table 8. Linked prerequisite and credit compliance options for energy efficiency

EAp2: Minimum
Energy Efficiency
Linked EAc2: Enhanced Energy Efficiency
(choose Option 1 OR Option 2)
Available
points
Option 1.
ASHRAE 90.1-2019

Prescriptive method
Option 1. Prescriptive Path
1–11
Option 1.
ASHRAE 90.1-2019

Prescriptive method

Path 2. Regulated Loads, Case 1. Additional efficiency
systems optimization
Reduce lighting power, increase HVAC and SWH equipment
efficiency, and/or reduce fan power.

1–4
Option 1.
ASHRAE 90.1-2019

Prescriptive method

AND/OR
+
Option 1.
ASHRAE 90.1-2019

Prescriptive method

Path 3. Plug and process loads

1–5
Option 1.
ASHRAE 90.1-2019

Prescriptive method

AND/OR

+
Option 1.
ASHRAE 90.1-2019

Prescriptive method

Path 4. Base building energy efficiency

2
Option 2.
ASHRAE 90.1-2022

Prescriptive method

Option 1. Prescriptive Path

3–12
Option 2.
ASHRAE 90.1-2022

Prescriptive method

Path 1.ASHRAE 90.1-2022 compliance for project scope.
Automatically achieved

3
Option 2.
ASHRAE 90.1-2022

Prescriptive method

AND
+
Option 2.
ASHRAE 90.1-2022

Prescriptive method
Path 2. Regulated loads
4
Option 2.
ASHRAE 90.1-2022

Prescriptive method

Case 1. Additional efficiency systems optimization. Reduce
lighting power, increase HVAC and SWH equipment efficiency,
and/or reduce fan power.
OR
Case 2. Additional efficiency requirements beyond ASHRAE
90.1 2022
(Applicable to substantial alterations)


Option 2.
ASHRAE 90.1-2022

Prescriptive method

Case 1. Additional efficiency systems optimization. Reduce
lighting power, increase HVAC and SWH equipment efficiency,
and/or reduce fan power.
OR
Case 2. Additional efficiency requirements beyond ASHRAE
90.1 2022
(Applicable to substantial alterations)

+

U.S. Green Building Council LEED v5 Reference Guide for Interior Design and Construction, April 2025 Launch Edition 167