Table 1. Points for renewable energy procurement

PointsTier 1Col3Col4Tier 2Tier 3
Points
Minimum rated
capacity1
ORPercent of tenant
annual site
energy

Percent of tenant
annual site
energy

Percent of
tenant annual
site energy
1A* 1 W / sq. ft.
(A * 10.8 W/sq.
m.)
OR
5%

20%

50%
2

A* 2 W / sq. ft.
(A* 21.6 W/sq.
m.)
OR
10%
40%
100%
3



20%
60%


4



35%

80%


5




100% Tier 1 and/or Tier 2 renewable
energy


100% Tier 1 and/or Tier 2 renewable
energy

*A = the sum of gross floor area of all floors of the building up to the three largest floors of the building, prorated to the project based on project area.

Renewable Energy Criteria

RENEWABLE ENERGY CLASSIFICATIONS

Tier 1. On-site Renewable Energy Generation or Social Impact Project

The renewable generation equipment may be located:

  • On the project site.

  • On the campus on which a project is located.

  • On the site of an equity project, as long as the renewable power system is provided, installed, and commissioned at no cost to the equity entity; that the ownership of the renewable power system is transferred to the equity entity; and that the rights to the power provided be given to the equity entity.

Tier 2. New Off-site Renewable Electricity

Off-site renewable electricity produced by new generation asset(s) must be:

  • Contracted to be operational within two years of building occupancy, OR

  • Contracted no more than five years after the renewable asset’s commercial operations date

Tier 3. Off-site Renewable Energy

  • Off-site renewable electricity that is Green-e® Energy certified or equivalent

  • Renewable fuels that are Green-e® Energy certified or equivalent

U.S. Green Building Council LEED v5 Reference Guide for Interior Design and Construction, April 2025 Launch Edition 186