Option 2. Energy Storage (1–2 points)

Provide on-site electric storage and/or thermal storage meeting the criteria in Table 2.

Include automatic load management controls capable of storing the electric or thermal energy during off-peak periods or periods with low grid carbon intensity, as well as using stored energy during on-peak periods or periods of high grid carbon intensity.

Table 2. Peak storage capacity relative to peak demand

Storage1 point2 points
Electric storage capacity
Relative to peak electric demand
0.2 kWh / kW
0.4 kWh / kW

Thermal storage capacity
Relative to peak coincident thermal demand
(heating + cooling + SWH + process heat)
1.0 kWh / kW
or Btu / Btu/hr
or ton-hr / ton
2.0 kWh / kW
or Btu / Btu/hr
or ton-hr / ton

AND/OR

Option 3. Demand Response Program (1 point)

Enroll in a minimum one-year demand response (DR) contract with a qualified DR program provider, with the intention of multiyear renewal.

On-site combustion-based electricity cannot be used to meet the demand-side management criteria.

AND/OR

Option 4. Automated Demand-Side Management (1 point)

On-site combustion-based electricity cannot be used to meet the demand-side management criteria.

PATH 1. SYSTEM-LEVEL CONTROLS (1 POINT)

Provide automated demand response controls for at least two of the following systems installed within the project scope of work:

  • HVAC systems (50% of rated capacity)

  • Lighting systems (50% of power)

  • Automatic receptacle controls (50% of number of receptacles)

  • Service water heating (90% of capacity)

  • Electric vehicle supply equipment

OR