DOCUMENTATION
Project
types
OptionsPathsDocumentation

All
Option 1.
Pre-
occupancy
air testing
Path 1 and
Path 2
Completed air quality testing report, including time,
date, testing methods complying with credit
requirements, results and limits of the tested
contaminants in all locations, and lab accreditation
scope for Path 2 VOCs if applicable.

All
Option 1.
Pre-
occupancy
air testing
Path 1 and
Path 2

Evidence of testing locations.

All
Option 1.
Pre-
occupancy
air testing
Path 1 and
Path 2
Document confirming substantial completion of
construction, highlighting the date. The intent is to
confirm that construction was complete prior to the
time/date of the air quality testing.

All
Option 2.
Continuous
Indoor Air
Monitoring
All
Evidence of monitoring locations and description of
monitoring approach.

All
Option 2.
Continuous
Indoor Air
Monitoring
All
Specifications of building grade air monitors.
REFERENCED STANDARDS

U.S. Green Building Council LEED v5 Reference Guide for Interior Design and Construction, April 2025 Launch Edition 355