APPENDIX I: LEED PLATINUM REQUIREMENTS
EAc1: Electrification Do not install new on-site combustion equipment in the project scope of work.
EAc2: Enhanced Energy Efficiency Seven points are required.
EAc3: Renewable Energy 100% of tenant annual site energy consumption is from any combination of Tier 1, Tier 2, and Tier 3 renewable energy.
MRc2: Reduce Embodied Carbon 10% reduction in embodied carbon.