4.2.2.2 Supplemental Information. Supplemental information necessary to verify compliance with this standard, such as calculations, worksheets, compliance forms, vendor literature, or other data, shall be made available when required by the building official .
4.2.2.3 Manuals. Operating and maintenance information shall be provided to the building owner. This information shall include but not be limited to the information specified in Sections 5.7.3.2, 6.7.3.2, 7.7.3.2, 8.7.3.2, 9.7.3.2, and 10.7.3.2. 4.2.3 Labeling of Material and Equipment. Materials and equipment shall be labeled in a manner that will allow for a determination of their compliance with the applicable provisions of this standard.
4.2.4 I nspections. All building construction, additions, or alterations work subject to the provisions of this standard shall remain accessible and exposed for inspection purposes until approved in accordance with the procedures specified by the building official . The building official, upon notification, shall make the inspections set forth in Section 4.2.4.1 through 4.2.4.6.
4.2.4.1 Fenestration Inspections. Fenestration shall be inspected in accordance with the compliance path selected in Section 4.2.1 and approved documentation provided in Section 4.2.2.
4.2.4.2 Opaque Assembly Thermal Insulation Inspections. Opaque assemblies shall be inspected in accordance with the compliance path selected in Section 4.2.1 and approved documentation provided in Section 4.2.2.
4.2.4.3 Continuous-Air-Barrier Inspections. Where a continuous air barrier is installed as a component of an opaque roof, above-grade walls and below-grade walls, or floors, it shall be inspected for compliance in accordance with Section 5.8.3.1. Integration with adjoining fenestration and other continuous air barrier elements shall be in accordance with Section 5.4.3.1.
4.2.4.4 Operable Fenestration and Door Inspections. Fenestration and door closers, inclusive of operating mechanisms, shall be installed in accordance with the manufacturer ’s installation instructions. Associated seals and gaskets shall be installed in accordance with the manufacturer ’s installation instructions and consistent with the provisions of Section 5.4.3.
4.2.4.5 Loading-Dock Weatherseals Inspections. Loading-dock weatherseals shall be inspected for installation and to verify that the seals are in good condition.
4.2.4.6 Other Inspections. Other inspections related to mechanical, plumbing, lighting, and other equipment shall be inspected in accordance with the compliance path selected in Section 4.2.1 and approved documentation provided in Section 4.2.2, or as otherwise required by the building official .
Informative Notes:
.1: CDs: ID V&T Provider, FPT Scope of Documentation + Verification. .2: BECx: Now required per ASHRAE IES Standard 202 or other standard. .3: Owner Letter to AHJ prior to Occupancy OR reports if AHJ asks. :)
- There are additional requirements within specific sections of this standard regarding documentation, procedures, independence of providers, and reporting. Requirements in individual sections are in addition to the general requirements provided in Section 4.2.5.
- See Informative Appendix H for additional commissioning guidance. 4.2.5.1 Building Systems Verification and Testing Requirements. Verification or functional perfor- mance testing ( FPT ) to confirm compliance with required provisions of this standard shall be performed on building systems, controls, and the building envelope, as required by Sections 5.9.1, 6.9.1, 7.9.1, 8.9.1, 9.9.1, 10.9.1, 12.2(e), and G1.2.1(e). Where testing is required but specific FPT procedures are not specified in this main verif design + install AB standard, testing shall use generally accepted engineering standards acceptable to the building official .
For alterations and additions, verification and testing (V&T) shall be performed for new systems, and their interface and integration with existing building systems shall be verified or tested.
4.2.5.1.1 Information on Building Permit Application. The following information shall be included on th e construction documents as part of the building permit application:
a. For systems that are required to comply with Section 4.2.5.1, the construction documents shall identify
V&T providers. b. V&T providers shall review the construction documents to verify that the relevant sensor locations,
devices, and control sequences are properly specified; performance and testing criteria are included; and equipment to be tested is accessible for testing and maintenance.