- Documentation of the training of operating personnel and building occupants on commissioned sys- tems, and a plan for the completion of any deferred trainings not completed at the time of report preparation
- A plan for the completion of commissioning and training, including climatic and other conditions required for performance of the deferred tests d. Final Commissioning Report. T he construction documents shall require the commissioning provider to
provide a final commissioning report to the owner before completion of the contractor’s general warranty period. 4.2.5.3 Activities Prior to Building Occupancy. B efore issuance of a certificate of occupancy, the V&T providers or commissioning provider shall complete the following activities:
a. Verification and FPT of the systems specified in Section 4.2.5.1 shall be completed and documented.
Exception to 4.2.5.3(a): Systems for which operation is seasonally dependent, and which cannot be fully
verified or tested at the time of occupancy, shall be functionally tested or commissioned when allowed for by post-occupancy operating conditions as determined by the commissioning or V&T providers. b. The owner shall be provided with the verification and FPT documentation as provided for in Section
4.2.5.1.2, or a preliminary commissioning report as provided for in Section 4.2.5.2.2. c. The owner shall provide the building official with one of the following:
- A copy of the reports listed in Section 4.2.5.3(b), if requested by the building official