9.6 Alternate Compliance Path (Reserved)

9.7 Submittals 9.7.1 General. Compliance documentation and supplemental information shall be submitted in accordance with Section 4.2.2.

9.7.2 Permit Application Documentation (Not Used) 9.7.3 Completion Requirements 9.7.3.1 Record Documents. Construction documents shall require that within 90 days after the date of system acceptance, record documents be provided to the property owner or the designated representative of the property owner. Record documents shall include, as a minimum, the location, luminaire identifier, control, and circuiting for each piece of lighting equipment .

9.7.3.2 Manuals. Construction documents shall require for all lighting equipment and lighting controls that an operating manual and maintenance manual be provided to the property owner or the designated representative of the property owner within 90 days after the date of system acceptance. These manuals shall include, at a minimum, the following:

a. Submittal data indicating all selected options for each piece of lighting equipment, including but not lim ited to lamps, ballasts, drivers, and lighting controls. b. Operation and maintenance manuals for each piece of lighting equipment and lighting controls with rou tine maintenance clearly identified including, as a minimum, a recommended relamping/cleaning program and a schedule for inspecting and recalibrating all lighting controls. c. A complete narrative of how each lighting control system is intended to operate, including recommended

settings.

9.7.3.3 Daylighting Documentation. The design documents shall identify all luminaires for general lighting that are located within daylight areas under skylights, daylight areas under roof monitors, and pri- mary sidelighted area and secondary sidelighted areas .

9.8 Product Information (Not Used)

9.9 Verification, Testing, and Commissioning 9.9.1 Verification and Testing. Lighting control devices and control systems shall be tested in accordance with this section and Section 4.2.5.1 to verify that control hardware and software are calibrated, adjusted, programmed, and in proper working condition in accordance with the construction documents and manufac- turer ’s installation instructions. The following procedures shall be performed for the type of controls listed:

a. Occupancy Sensors

  1. Certify that the sensor has been located and aimed in accordance with manufacturer recommendations.
  2. For projects with up to seven (7) occupancy sensors, all occupancy sensors shall be tested.
  3. For projects with more than seven (7) occupancy sensors, testing shall be performed for each unique combination of sensor type and space geometry. i. For each sensor to be tested, verify the following: (a) Status indicator (as applicable) operates correctly. (b) Controlled lights turn off or down to the permitted level within the required time. (c) For auto-ON occupancy sensors, the lights turn on to the permitted level when someone enters

the space. (d) For manual -ON sensors, the lights turn on only when manually activated. (e) The lights are not incorrectly turned on by movement in nearby areas or by HVAC operation. b. Automatic Time Switches

  1. Confirm that the automatic time-switch control is programmed with weekday, weekend, and holiday (as applicable) schedules.
  2. Document for the owner automatic time-switch programming, including weekday, weekend, and holiday schedules, as well as all setup and preference program settings.
  3. Verify that correct time and date are properly set in the time switch.
  4. Verify that any battery backup (as applicable) is installed and energized.
  5. Verify that the override time limit is set to no more than two (2) hours.
  6. Simulate occupied condition. Verify and document the following: i. All lights can be turned on and off by their respective area control switch.