ASHRAE-90.1-2022- - Page 221
Extracted Content
Table 12.5.1 Modeling Requirements for Calculating Design Energy Cost and Energy Cost Budget (Continued)
| Proposed Design (Column A) Design Energy Cost (DEC) | Budget Building Design (Column B) Energy Cost Budget (ECB) |
|---|---|
| 11. Service Water-Heating Systems | |
The service water-heating system type and all related performance parameters, such as equipment capacities and efficiencies, in the proposed design shall be determined as follows:
|
The service water-heating system type in the budget building design shall be identical to the proposed design. The service water-heating system performance of the budget building design shall meet the requirements of Sections 7.4 and 7.5.
Exceptions:
Service water loads and use shall be the same for both the proposed design and baseline building design and typical of the proposed building type. Piping losses shall not be modeled. |
| 12. Miscellaneous Loads | |
Receptacle, motor, and process loads shall be modeled and estimated based on the building area type or space type category and shall be assumed to be identical in the proposed and budget building designs. These loads shall be included in simulations of the building and shall be included when calculating the energy cost budget and design energy cost. All end-use load components within and associated with the property shall be modeled, unless specifically excluded by Table 12.5.1(14), including but not limited to exhaust fans, parking garage ventilation fans, exterior property lighting, swimming pool heaters and pumps, elevators and escalators, and cooking equipment.
| Same as proposed design. |
| 13. Refrigeration | |
| Where refrigeration equipment in the proposed design is rated in accordance with AHRI 1200, the rated energy use shall be modeled. Otherwise, the proposed design shall be modeled using the actual equipment capacities and efficiencies. | Where refrigeration equipment is specified in the proposed design and listed in Table 6.8.1-11, the budget building design shall be modeled as specified in Table 6.8.1-11 using the actual equipment capacities. If the refrigeration equipment is not listed in Table 6.8.1-11, the budget building design shall be modeled the same as the proposed design. |
| 14. Modeling Exceptions | |
| All elements of the proposed design building envelope, HVAC, service water heating, lighting, and electrical systems shall be modeled in the proposed design in accordance with the requirements of Table 12.5.1(1) through (13). | None. |



ANSI/ASHRAE/IES Standard 90.1-2022 (I-P) 219