Table G3.1.1-3 Baseline HVAC System TypesCol2Col3
Building Area Types a, Number of Stories b, and
Combined Floor Area c
Climate Zones 3B, 3C, and 4 to 8Climate Zones 0 to 3A
Residential
System 1—PTACSystem 2—PTHP
Public assembly area smaller than 120,000 ft2
System 3—PSZ-ACSystem 4—PSZ-HP
Public assembly area equal to or larger than120,000 ft2System 12—SZ-CV-HWSystem 13—SZ-CV-ER
Heated-only storageSystem 9—Heating and_ventilation_System 10—Heating and_ventilation_
Retail in a_building_ that is 1 or 2_stories_System 3—PSZ-ACSystem 4—PSZ-HP
Hospital that is either
• larger than 150,000 ft2 or
• in a_building_ greater than 5_stories_.
System 7—VAV with_reheat_System 7—VAV with_reheat_
Hospital—all otherSystem 5—Packaged_VAV_ with
reheat
System 5—Packaged_VAV_ with_reheat_
Other_Nonresidential_ area that is both
• smaller than 25,000 ft2 and
• in a_building_ 3_stories_ or fewer.
System 3—PSZ-ACSystem 4—PSZ-HP
Other_Nonresidential_ area that is both
• smaller than 25,000 ft2 and
• in a_building_ with 4 or 5_stories_.
System 5—Packaged_VAV_
with_reheat_
System 6—Packaged_VAV_ with PFP
boxes
Other_nonresidential_ area that is both
• 25,000 ft2 to 150,000 ft2 and
• in a_building_ that is 5_stories_ or fewer.
System 5—Packaged_VAV_
with_reheat_
System 6—Packaged_VAV_ with PFP
boxes
Other_Nonresidential_ area that is either
• larger than 150,000 ft2 or
• in a_building_ greater than 5_stories_.
System 7—VAV with_reheat_System 8—VAV with PFP boxes

a. Building area type determined in accordance with Section G3.2.1.1. b. The total number of stories in a building, including above-grade and below-grade stories but not including stories solely devoted to parking. c. Combined gross conditioned floor area and semiheated floor area, of the building area type, based on the requirements of Section G3.2.1.1.

Table G3.1.1-4 Baseline System Descriptions

System No.System TypeFan ControlCooling Type aHeating Type a
1. PTACPackaged terminal air conditionerConstant volumeDirect expansionHot-water_fossil fuel_ boiler
2. PTHPPackaged terminal heat pumpConstant volumeDirect expansionElectric heat pump
3. PSZ-ACPackaged rooftop air conditionerConstant volumeDirect expansionFossil fuel furnace
4. PSZ-HPPackaged rooftop heat pumpConstant volumeDirect expansionElectric heat pump
5. Packaged_VAV_ with
reheat
Packaged rooftop_VAV_ with_reheat_VAVDirect expansionHot-water_fossil fuel_ boiler
6. Packaged_VAV_ with
PFP boxes
Packaged rooftop_VAV_ with parallel
fan power boxes and_reheat_
VAVDirect expansionElectric resistance
7. VAV with_reheat_VAV with_reheat_VAVChilled waterHot-water_fossil fuel_ boiler
8. VAV with PFP boxesVAV with parallel fan-powered boxes
and_reheat_
VAVChilled waterElectric resistance
9. Heating and_ventilation_Warm air furnace, gas firedConstant volumeNoneFossil fuel furnace
10.Heating and_ventilation_Warm air furnace, electricConstant volumeNoneElectric resistance
11.SZ–VAVSingle-zone_VAV_VAVChilled waterSee note (b).
12.SZ-CV-HWSingle-zone systemConstant volumeChilled waterHot-water_fossil fuel_ boiler
13.SZ-CV-ERSingle-zone systemConstant volumeChilled waterElectric resistance