Table H-2 Typical Commissioning (Cx) Process Activities, Deliverables and Responsibilities [ a]

ItemActivityDeliverable90.1 SectionNormally Provided byPhase
1Owner’s Project Requirements
(OPR)
OPR documentNROwner with assistance from design
and_Cx_ teams
Predesign
2Basis of Design (BoD)BoD documentNRDesign teamDesign through
construction
3Cx planCx plan document4.2.5.2.2Cx provider with input from
owner, design team, and contractor
Predesign
4Contractor_Cx_ requirementsCx specifications4.2.5.1.1,
4.2.5.2.1,
6.9.2
Design team and
Cx provider
Design
5Design review, including
Standard 90.1 compliance review
Cx design review report
4.2.5.2,
4.2.5.2.2
Cx providerDesign
6Submittal reviewSubmittal review report bNRCx providerConstruction
7Commission designated systems,
inspections,FPT
Installation, inspection,
functional test reports,
performance test reports b
4.2.5.1,
4.2.5.2
Contractors,manufacturers, Cx
provider, and_Cx provider team_
Construction
8Track identified issues to
resolution
Issues and resolution log b4.2.5.1,
4.2.5.2
Cx provider and teamConstruction
9Systems manualSystems manual review
Review NRContractors with review by
Cx provider
Construction
10TrainingTraining plan and reports bNRContractors and_manufacturers_
with review by_Cx provider_
Final
11Preliminary_Cx_ reportPreliminary
Cx report
4.2.5.2.1,
4.2.5.2.2
Cx providerConstruction
12Cx activities during occupancyAdditional information
and updates to reports b
NRCx provider and_building_
operations
Final
13Final_Cx_ reportFinal_Cx_ Report4.2.5.2.2Cx providerFinal

a. NR = not required by Standard 90.1; Cx = commissioning. b. Noted interim or partial deliverables are typically included in the preliminary and final commissioning reports.

gested items to verify in that section. There are specific verification, commissioning, or testing activities required by Standard 90.1 in Sections 4.2.5, 5.9, 6.9, 7.9, 8.9, 9.9, 10.9, 12.2(e), and G1.2.1(e). Table H-3 lists only the items in Standard 90.1 that would be beneficial to include in a commissioning scope. While these requirements cover many of the building components, they are not comprehensive, and there are benefits available from additional commissioning or testing. There are other items outside the scope of Standard 90.1 that would typically be included in a commissioning scope that are not covered here but that may improve the quality and reliability of the building systems and assemblies.

The suggested commissioning activities are intended to be included in a commissioning scope based on the building owner’s perception of desired outcomes relative to the particular building program and location and based on the experience of the commissioning provider . The activities are summarized in a checklist format and are related to the requirements that are described in the noted subsections of Standard 90.1. The scope of the items to verify should include verification of compliance with Standard 90.1 requirements by documenting each item’s applicability, inclusion, or exception. Included items should be verified for installation, proper configuration, and operation. Depending on the comprehensiveness of the commissioning effort, verification for certain items may be included at the design phase, construction phase, or both. Verification that the design and construction meet the requirements of the chosen compliance path in Standard 90.1 could be completed using the verification and compliance forms from the Standard 90.1 User’s Man- ual . Table H-3 could be used as a commissioning scope development checklist, and for each item the status for the subject building could be noted as follows:

NA = not applicable (Either the item is not in the proposed building, an exception was used, or the item or prescriptive requirement was traded off in the performance path.)

Cx = commissioned, verified, or tested