Table H-2 Typical Commissioning (Cx) Process Activities, Deliverables and Responsibilities [ a]
| Item | Activity | Deliverable | 90.1 Section | Normally Provided by | Phase |
|---|---|---|---|---|---|
| 1 | Owner’s Project Requirements (OPR) | OPR document | NR | Owner with assistance from design and_Cx_ teams | Predesign |
| 2 | Basis of Design (BoD) | BoD document | NR | Design team | Design through construction |
| 3 | Cx plan | Cx plan document | 4.2.5.2.2 | Cx provider with input from owner, design team, and contractor | Predesign |
| 4 | Contractor_Cx_ requirements | Cx specifications | 4.2.5.1.1, 4.2.5.2.1, 6.9.2 | Design team and Cx provider | Design |
| 5 | Design review, including Standard 90.1 compliance review | Cx design review report | 4.2.5.2, 4.2.5.2.2 | Cx provider | Design |
| 6 | Submittal review | Submittal review report b | NR | Cx provider | Construction |
| 7 | Commission designated systems, inspections,FPT | Installation, inspection, functional test reports, performance test reports b | 4.2.5.1, 4.2.5.2 | Contractors,manufacturers, Cx provider, and_Cx provider team_ | Construction |
| 8 | Track identified issues to resolution | Issues and resolution log b | 4.2.5.1, 4.2.5.2 | Cx provider and team | Construction |
| 9 | Systems manual | Systems manual review | Review NR | Contractors with review by Cx provider | Construction |
| 10 | Training | Training plan and reports b | NR | Contractors and_manufacturers_ with review by_Cx provider_ | Final |
| 11 | Preliminary_Cx_ report | Preliminary Cx report | 4.2.5.2.1, 4.2.5.2.2 | Cx provider | Construction |
| 12 | Cx activities during occupancy | Additional information and updates to reports b | NR | Cx provider and_building_ operations | Final |
| 13 | Final_Cx_ report | Final_Cx_ Report | 4.2.5.2.2 | Cx provider | Final |
a. NR = not required by Standard 90.1; Cx = commissioning. b. Noted interim or partial deliverables are typically included in the preliminary and final commissioning reports.
gested items to verify in that section. There are specific verification, commissioning, or testing activities required by Standard 90.1 in Sections 4.2.5, 5.9, 6.9, 7.9, 8.9, 9.9, 10.9, 12.2(e), and G1.2.1(e). Table H-3 lists only the items in Standard 90.1 that would be beneficial to include in a commissioning scope. While these requirements cover many of the building components, they are not comprehensive, and there are benefits available from additional commissioning or testing. There are other items outside the scope of Standard 90.1 that would typically be included in a commissioning scope that are not covered here but that may improve the quality and reliability of the building systems and assemblies.
The suggested commissioning activities are intended to be included in a commissioning scope based on the building owner’s perception of desired outcomes relative to the particular building program and location and based on the experience of the commissioning provider . The activities are summarized in a checklist format and are related to the requirements that are described in the noted subsections of Standard 90.1. The scope of the items to verify should include verification of compliance with Standard 90.1 requirements by documenting each item’s applicability, inclusion, or exception. Included items should be verified for installation, proper configuration, and operation. Depending on the comprehensiveness of the commissioning effort, verification for certain items may be included at the design phase, construction phase, or both. Verification that the design and construction meet the requirements of the chosen compliance path in Standard 90.1 could be completed using the verification and compliance forms from the Standard 90.1 User’s Man- ual . Table H-3 could be used as a commissioning scope development checklist, and for each item the status for the subject building could be noted as follows:
NA = not applicable (Either the item is not in the proposed building, an exception was used, or the item or prescriptive requirement was traded off in the performance path.)
Cx = commissioned, verified, or tested