Table H-3 Standard 90.1 Items to Verify
| Subsection | Subsection Title | Standard 90.1 Items to Verify for Proper Operation or Inclusion | Status |
|---|---|---|---|
| 4.2.5.2 | Building Commissioning Requirements | Document in sufficient detail compliance of the_building_ and its components, assemblies, controls, and_systems_ with required provisions of this standard. | |
| 5.4.1 | Insulation | Design details maintain continuity of thermal barrier. | |
| 5.4.3.2 | Continuous Air Barrier Design and Installation | Air barriers meet the following: • Air barrier design and installation per Section 5.4.3.2 and either • whole-building air leakage testing per Section 5.4.3.1 or • design and installation verification program performed in accordance with Section 5.4.3.1 and Section 5.9.1.2. | |
| 5.8.3.1 | Testing, Acceptable Materials, and Assemblies | Continuous air barrier materials and assemblies comply with specific manufacturer requirements or are tested for leakage resistance. | |
| 5.8.3.2 | Fenestration and Doors | Fenestration and_doors_ have_manufacturer_ documentation that_air leakage_ does not exceed allowable_air leakage_ rates. | |
| 5.5.4.2 | Fenestration Area | Fenestration to_wall_ ratio and_skylight_ to_roof_ ratio meet either the prescriptive requirements or the_proposed design_ in the performance path, depending on the compliance path used. | |
| 5.8.1 | Insulation | Insulation material meets design specifications and is continuous. | |
| 5.9 | Verification, Testing, and Commissioning | Envelope assemblies and_fenestration_ comply with requirements.Building envelope performance is tested or verified. | |
| 6.3.2 | Criteria | HVAC_equipment_ meets_efficiency_ criteria and controls function properly. | |
| 6.4.1 | Equipment Efficiencies, Verification, and Labeling Requirements | Equipment selected meets the minimum_efficiency_ requirements and is correctly_labeled._ | |
| 6.4.2 | Calculations | HVAC_equipment_ matches load and_pump_ head calculations. | |
| 6.4.3.1/ 6.4.3.2 | Zone Thermostatic Controls/ Set-Point Overlap Restriction | Zoning pattern and_dead band_ setting configured properly, including_VAV_ zone controls. Heating and cooling_set points_ do not overlap. | |
| 6.4.3.3 | Off-Hour Controls | Off-hour control,automatic shutdown,setback controls, optimum start control, and zone isolation are properly configured where applicable. | |
| 6.4.3.4 | Ventilation System Controls | Stair and shaft_automatic_ damper function, shutoff damper control, damper leakage performance, ventilation fans, and enclosed parking garage control systems operate per code. | |
| 6.4.3.5 | Heat-Pump Auxiliary Heat Control | Heat-pump auxiliary heat control properly configured. | |
| 6.4.3.6 | Humidifier Preheat | Automatic shutoff valve with configured controls. | |
| 6.4.3.6 | Humidification and Dehumidification Control | No simultaneous humidification and dehumidification operation. | |
| 6.4.3.7 | Freeze Protection and Ice/Snow Melt | Automatic shutoff based on outdoor temperature or precipitation. | |
| 6.4.3.8 | Ventilation Controls for High-Occupancy Areas | Demand control ventilation (DCV) system where applicable. | |
| 6.4.3.10 | Single-Zone VAV Control | Single-zone systems have multispeed or_VAV_ control properly configured. | |
| 6.4.4.1 | HVAC System Insulation | Insulation for ductwork,piping, heating panels, and radiant floor heating systems correct and continuous. | |
| 6.4.4.2 | Ductwork and Plenum Leakage | Duct sealing complete, and required leakage tests performed. |
ANSI/ASHRAE/IES Standard 90.1-2022 (I-P) 349