energy efficiency are working properly, the commissioning plan is useful in providing the building official with assurance that required are in place, where the building official may not have to time or expertise to investigate proper operation. Issues that are unresolved are also identified, as are items that will be tested after occupancy.
H5.9 Final Commissioning Report (See Section 4.2.5.2.2). A final commissioning report is provided by the commissioning provider once all testing is complete. While the final commissioning report is delivered after the occupancy permit, the requirement for it in the construction documents supports the energy effi- ciency goals of Standard 90.1 by providing a future report that will address issues that cannot be resolved at the time of occupancy permit issuance.