8.2.8 OCx has the following key activities:
a. Maintaining the OPR to reflect changes in use and opera tion of the facility b. Maintaining the BoD to reflect changes in systems and
assemblies due to renovations or in response to changes in the OPR c. Periodic evaluation of achieving the current OPR and
against previous benchmarks by appropriate tests d. Maintaining the Systems Manual to reflect changes in
OPR, BoD, and systems/assemblies e. Ongoing training of O&M personnel and occupants on
current OPR and BoD and changes in systems and assemblies
8.3 Occupancy and Operations Phase Acceptance Requirements
8.3.1 The Cx should include the formal acceptance by the CxP and the Owner of any deferred training, the final project Systems Manual, and the final Cx Report during the Occupancy and Operations Phase.
8.4 Occupancy and Operations Phase Documentation Requirements
8.4.1 The final project Cx Report and final project Systems Manual are the primary documentation requirements for the
Occupancy and Operations Phase Cx. The information in these deliverables is used throughout the life of the facility.
8.4.2 If periodic performance verification is conducted for the Owner, an Ongoing Cx Report and updates (as necessary) to training and the Systems Manual should be provided as deliverables.
8.5 Occupancy and Operations Phase Training Requirements
8.5.1 The Cx training requirements for the Occupancy and Operations Phase are discussed in Section 8.2.4.
9. REFERENCES
- DeVor, R., T. Chang, and J. Sutherland. 1992. Statistical
Quality Control: Contemporary Concepts and Meth- ods, Chapter 7. New York: Macmillan Publishing Company. 2. Gitlow, H., and S. Gitlow. 1987. The Deming Guide to
Quality and Competitive Position, Chapter 3. Englewood Cliffs, NJ: Prentice-Hall. 3. Juran, J.M. (Ed.). 1995. A History of Managing for Qual-
ity: The Evolution, Trends, and Future Directions of Managing for Quality . Milwaukee, WI: ASQC Quality Press.
ASHRAE Guideline 0-2019 17