d. Key milestones that need to be reviewed e. Updated lists of specialists required to implement the Cx
based on the actual design and interrelationship with other systems and assemblies f. List of items to be included in the construction documents g. Lists of priority items related whenever possible to safety,
health, energy, environmental impact, aesthetics, and O&M, in addition to the OPR h. List of construction checklists to be used by the contractor i. Samples of construction checklists (Examples of construction checklists are included in Informative Appendix M to this guideline and in other appendices in other supplementary technical guidelines, such as ASHRAE Guideline 1.1, HVAC&R Technical Requirements for the Commissioning Process .) j. List of items to be included in the Systems Manual, such as parts lists, troubleshooting needs, O&M requirements, system description, and the level at which each set of materials needs to be written for clear understanding k. List of training requirements, timing, learning outcomes l. List of tests that need to be performed m. List of items required for acceptance of Design Phase
commissioning
A8. SECTION 7, CONSTRUCTION PHASE
The following should be included in the Construction Phase section for [ insert topic ]:
a. List of test procedures and data forms to verify achieve ment of OPR and BoD b. Samples of test procedures and data forms (Examples of
these are included in Informative Appendix U to other supplementary technical guidelines, such as ASHRAE Guideline 1.1, HVAC&R Technical Requirements for the Commissioning Process .) c. List of coordination requirements and items provided by
others d. List of specific items for the site visit procedures e. Tests needs and schedule f. CxP Team meetings g. Issues and resolution logs h. Input into the final Cx Report i. Lessons-learned workshop schedule during Occupancy and Operations Phase j. List of items required for acceptance of Construction Phase commissioning
A9. SECTION 8, OCCUPANCY AND OPERATIONS PHASE
The following should be included in the Occupancy and Operations Phase section for [ insert topic ]:
a. List of training items to be accomplished during the first
year of operation b. List of warranty items to be checked during the first year
of operation c. List test requirements during occupancy, including peri odic retesting for a successful continuous operation of the facility
d. List who should attend the lessons-learned workshop e. List of criteria to be included in the final Cx Report f. List of items required for acceptance of Occupancy and Operations Phase commissioning
A10. SECTION 9, REFERENCES
Include industry-specific references that support recommendations for benchmarking, testing, and other supporting guidance in the development of the OPR, BoD, tests, and other Cx documents.
A11. APPENDICES
Appendices are to be used to provide additional information, examples of documentation, examples of specifications, acceptance procedure details, and other items that are not required to achieve compliance with the technical guideline but will assist in implementing the Cx for the specific technical system or assembly. This is the place to illustrate best practices and to provide information on how to achieve best practice and economy in design. Appendix Q, “References,” should provide current articles, guides, and other information on implementing the Cx for the specific supporting technical requirements guidelines.
The desired goal is to have all Cx guidelines use the same appendix designation (i.e., appendix letter and title) as Guideline 0. If an appendix is not required, it should specifically be so noted in each technical guideline—suggested wording: “This appendix is intentionally left blank” or “There is no supplemental information required for [ insert assembly or system ] technology.” Appendix A will be empty in all supplemental guidelines. Appendix B is specific to Guideline 0 and should not be changed in supplemental guidelines. Appendices C through E may require no modification for most supplemental guidelines.
The list and numbering of appendices, to be in compliance with Guideline 0, must be as follows:
-
Appendix A—Guide for Developing Supplementary Technical Guidelines for the Commissioning Process [ used only in Guideline 0 ]
-
Appendix B—Commissioning Process Flowchart [ used only in Guideline 0 ]
-
Appendix C—Cost and Benefits of the Commissioning Process [ typically only used in Guideline 0 ]
-
Appendix D—Commissioning Process Documentation Matrix [ typically only used in Guideline 0 ]
-
Appendix E—Commissioning Process Request for Qualifications [ typically only used in Guideline 0 ]
-
Appendix F—Roles and Responsibilities
-
Appendix G—Cx Plan
-
Appendix H—Acceptance Plan
-
Appendix I—Owner’s Project Requirements Workshop Guidance
-
Appendix J—Owner’s Project Requirements
-
Appendix K—Basis of Design
-
Appendix L—Specifications
-
Appendix M—Construction Checklists
ASHRAE Guideline 0-2019 19