s. Supervise the CxP Team members in completion of tests. The test data will be part of the Cx Report. t. Periodically review record drawings for accuracy with respect to the installed systems. Request revisions to achieve accuracy. u. Verify that the Systems Manual and all other design and
construction records have been updated to include all modifications made during the Construction Phase. v. Repeat implementing of tests to accommodate seasonal
tests or to correct any performance deficiencies. Revise and resubmit the Cx Report. w. Prepare the final Cx Report. x. Assemble the final documentation, which includes the Cx
Report, the Systems Manual, and all record documents. Submit this documentation to the Owner for review and acceptance. y. Recommend acceptance of the individual systems and
assemblies to the Owner (in accord with the defined project requirements).
F3. DESIGN PROFESSIONAL
a. Participate and assist in the documentation of the initial
OPR. b. Document revisions to the OPR and obtain approval from
the Owner. c. Document the BoD. d. Prepare contract documents, including the integration of
the Cx requirements and activities provided by the CxP. e. Prepare contract documents that coordinate required inter faces between systems and assemblies. f. Attend the Predesign Phase and Design Phase coordination and review meetings. g. Respond to CxP Team design submission review com ments and other issues in a timely manner. h. Attend the prebid and preconstruction meetings as sched uled by the CxP. i. Specify and verify that the O&M of the systems and assemblies has been adequately detailed in the construction documents. j. Review and incorporate as appropriate the CxP’s comments from submittal reviews. k. Participate in the initial O&M personnel and occupant
training session by presenting the project BoD. l. Participate in other training as detailed in the training program. m. Review test procedures submitted by the contractor. n. Review and comment on the CxP’s periodic Cx Progress
Reports and issues and resolution log reports. o. Review and accept record documents as required by con tract documents. p. Review and comment on the final Cx Report. q. Recommend final acceptance of the systems to the Owner.
F4. CONSTRUCTION MANAGER
a. Include costs for Cx Activities in the contract price. b. Include Cx Activities and requirements in all contractors’
contracts. c. Provide adequate accessibility as required to properly
operate and maintain the facility. d. Provide acceptable representation with the means and
authority to prepare and coordinate implementation of the Cx as detailed in the contract documents. e. Issue a statement certifying that all work has been com pleted and that the facility is operational, in accordance with contract documents. f. Issue the appropriate final reports to the design professionals for review and acceptance. g. Remedy deficiencies identified by the CxP during verifi cation of the installation or testing. h. Review and comment on the final Cx Report.
F5. CONTRACTOR
a. Include costs for Cx Activities in the contract price. b. Include Cx Activities and requirements in each purchase
order or subcontract written. c. Obtain cooperation and participation of all subcontractors
and manufacturers. d. Attend the preconstruction and CxP Team meetings. e. Include Cx milestones in the project schedule. f. Implement the training program as detailed in the contract documents. g. Provide submittals to the Owner, design professionals,
and the CxP. h. Notify the CxP when systems and assemblies are ready
for testing. i. Demonstrate the performance of assemblies and/or operation of systems to the CxP. j. Complete the construction checklists as the work is accomplished. Provide the completed construction checklists to the CxP. k. Continuously maintain the record drawings and submit as
detailed in the contract documents.
F6. MANUFACTURERS
a. Provide all information required for the O&M of the sys tem or assembly as part of the initial submittal. b. Provide the requirements to maintain the warranty as part
of the initial submittal. c. Coordinate and accomplish factory tests as detailed in the
contract documents. d. Provide training as detailed in the training program con tained in the contract documents. e. Demonstrate operation and performance of the system or
assembly as detailed in the contract documents.