b. The CxP directs the completion of system and assembly
testing by the contractor and documents the results. c. The CxP works with the contractor in resolving any issues
identified during testing. d. The CxP verifies that all system documentation is received
from the contractor. e. The CxP presents a preliminary Construction Phase Cx
Report prior to occupancy that provides an evaluation of meeting each element of the OPR, including recommendations to the Owner for acceptance/rejection of the facility. f. The CxP provides a final Construction Phase Cx Report with details on the Cx Activities completed during the Construction Phase.
H4. OCCUPANCY AND OPERATIONS PHASE
The updated OPR, updated BoD, updated Systems Manual, seasonal test results, and Cx Report are formally accepted by the Owner during the Occupancy and Operations Phase. The OPR, BoD, and Systems Manual follow the same process as previously detailed.
The general process for accepting the seasonal test results is as follows:
a. The CxP directs the completion of seasonal system and
assembly testing by the contractor and documents the results. b. The CxP works with the contractor in resolving any issues
identified during testing. c. The CxP verifies that all updated system documentation is
received from the contractor. d. The CxP recommends to the Owner acceptance of the sea sonal testing results.
The general process for accepting the Cx Report is as follows:
a. The CxP provides the Cx Report to the Owner, design
professionals, and contractor for review and comment. b. The CxP incorporates comments and provides a final copy
to the CxP Team members. c. The Owner accepts the Cx Report, ending the CxP’s
responsibilities.
ASHRAE Guideline 0-2019 33