Table L-1 Description of Specification Sections

Section
Number
Document/SectionList of ContentsScope of Contents
01100SUMMARY• Work covered by contract
documents
• Identification of separate prime
contractors
• Describe Cx Activities as a part of the project.
• Alert the contractor that the Owner has contracted for
commissioning with a separate CxP.
• Delineate scope of Cx.
01290PAYMENT PROCEDURESNo special Cx requirements
01310PROJECT MANAGEMENT
AND COORDINATION
Provisions about coordination of Cx
Activities among contractors and
subcontractors; project meetings
• Add requirements to include CxP in coordination
meetings (particularly “Preconstruction Meeting”).
• Coordinate meetings and conferences.
01330SUBMITTAL PROCEDURESProcedures for submittals• Submittal requirements for Cx Activity reports and
schedules should be specified in Sections 01811 to
01819.
• Add requirements here for additional copies from
contractor to CxP and for approved submittals to be
distributed to CxP.
01400QUALITY REQUIREMENTSCoordinate with Cx Activities, witnessing of tests, and
test reports.
01500TEMPORARY FACILITIES
AND CONTROLS
Include office space for CxP and utility services for Cx
Activities.
01600PRODUCT REQUIREMENTSNo special Cx requirements
01731CUTTING AND PATCHINGNo special Cx requirements
01770CLOSEOUT PROCEDURESInclude key Cx milestones to achieve substantial
completion and closeout.
01782OPERATION AND
MAINTENANCE DATA
• Include requirements for CxP to review and
recommend approval of Systems Manual.
• Same procedures as described for Section 01330
Submittals.
01810GENERAL
COMMISSIONING
REQUIREMENTS
General administrative and procedural requirements
without regard to specific systems and assemblies
01811BUILDING ASSEMBLY
CX REQUIREMENTS
• Substructure
• Superstructure
• Building shell
• Exterior wall assemblies
• Roof assemblies
• Building interior
• Separations
• Paths of egress
• Lists of construction checklists
• Prerequisites to testing
• System or assembly test requirements
• Test reports
01812CONVEYING SYSTEM
CX REQUIREMENTS
• Elevators and lifts
• Escalators and moving walks
• Lists of construction checklists
• Prerequisites to testing
• System or assembly test requirements
• Test reports
01813PROTECTIVE SYSTEM
CX REQUIREMENTS
• Fire suppression (including pumps,
sprinkler and standpipe piping, and
terminal devices)
• Detection and alarms (including
fire, smoke, gas, and leak)
• Lightning protection (this is not
part of electrical distribution)
• Cathodic protection (this is not part
of electrical distribution)
• Lists of construction checklists
• Prerequisites to testing
• System or assembly test requirements
• Test reports

ASHRAE Guideline 0-2019 41