Table L-1 Description of Specification Sections
| Section Number | Document/Section | List of Contents | Scope of Contents |
|---|---|---|---|
| 01100 | SUMMARY | • Work covered by contract documents • Identification of separate prime contractors | • Describe Cx Activities as a part of the project. • Alert the contractor that the Owner has contracted for commissioning with a separate CxP. • Delineate scope of Cx. |
| 01290 | PAYMENT PROCEDURES | No special Cx requirements | |
| 01310 | PROJECT MANAGEMENT AND COORDINATION | Provisions about coordination of Cx Activities among contractors and subcontractors; project meetings | • Add requirements to include CxP in coordination meetings (particularly “Preconstruction Meeting”). • Coordinate meetings and conferences. |
| 01330 | SUBMITTAL PROCEDURES | Procedures for submittals | • Submittal requirements for Cx Activity reports and schedules should be specified in Sections 01811 to 01819. • Add requirements here for additional copies from contractor to CxP and for approved submittals to be distributed to CxP. |
| 01400 | QUALITY REQUIREMENTS | Coordinate with Cx Activities, witnessing of tests, and test reports. | |
| 01500 | TEMPORARY FACILITIES AND CONTROLS | Include office space for CxP and utility services for Cx Activities. | |
| 01600 | PRODUCT REQUIREMENTS | No special Cx requirements | |
| 01731 | CUTTING AND PATCHING | No special Cx requirements | |
| 01770 | CLOSEOUT PROCEDURES | Include key Cx milestones to achieve substantial completion and closeout. | |
| 01782 | OPERATION AND MAINTENANCE DATA | • Include requirements for CxP to review and recommend approval of Systems Manual. • Same procedures as described for Section 01330 Submittals. | |
| 01810 | GENERAL COMMISSIONING REQUIREMENTS | General administrative and procedural requirements without regard to specific systems and assemblies | |
| 01811 | BUILDING ASSEMBLY CX REQUIREMENTS | • Substructure • Superstructure • Building shell • Exterior wall assemblies • Roof assemblies • Building interior • Separations • Paths of egress | • Lists of construction checklists • Prerequisites to testing • System or assembly test requirements • Test reports |
| 01812 | CONVEYING SYSTEM CX REQUIREMENTS | • Elevators and lifts • Escalators and moving walks | • Lists of construction checklists • Prerequisites to testing • System or assembly test requirements • Test reports |
| 01813 | PROTECTIVE SYSTEM CX REQUIREMENTS | • Fire suppression (including pumps, sprinkler and standpipe piping, and terminal devices) • Detection and alarms (including fire, smoke, gas, and leak) • Lightning protection (this is not part of electrical distribution) • Cathodic protection (this is not part of electrical distribution) | • Lists of construction checklists • Prerequisites to testing • System or assembly test requirements • Test reports |