ASHRAE_Guideline_0-2019_ - Page 044
Extracted Content
Table L-1 Description of Specification Sections (Continued)
| Section Number | Document/Section | List of Contents | Scope of Contents |
|---|---|---|---|
| 01814 | PLUMBING SYSTEM COMMISSIONING REQUIREMENTS | • Water distribution • Sanitary waste • Storm drainage • Other plumbing systems | • Lists of construction checklists • Prerequisites to testing • System or assembly test requirements • Test reports |
| 01815 | HVAC&R SYSTEM COMMISSIONING REQUIREMENTS | • Heat generation (including central equipment, distribution systems, and terminal devices) • Refrigeration (including central equipment, distribution systems, and terminal devices) • Ventilation (including central equipment, distribution systems, and terminal devices) • HVAC control systems (including central equipment, distribution systems, and terminal devices) | • Lists of construction checklists • Prerequisites to testing • System or assembly test requirements • Test reports |
| 01816 | ELECTRICAL SYSTEM COMMISSIONING REQUIREMENTS | • Power distribution (including central equipment, distribution circuits, and terminal devices) • Lighting (including fixtures and controls) | • Lists of construction checklists • Prerequisites to testing • System or assembly test requirements • Test reports |
| 01817 | COMMUNICATIONS SYSTEMS COMMISSIONING REQUIREMENTS | • Voice and data • Sound and video | • Lists of construction checklists • Prerequisites to testing • System or assembly test requirements • Test reports |
| 01818 | ELECTRONIC SAFETY AND SECURITY SYSTEMS Cx REQUIREMENTS | • Security access, perimeter security, intrusion detection, alarm and detection systems (including fire and smoke and leak detection) | • Lists of construction checklists • Prerequisites to testing • System or assembly test requirements • Test reports |
| 01820 | DEMONSTRATION INDIVIDUAL SECTIONS IN DIVISIONS 2 THROUGH 16 | • Field quality control tests • Adjusting and balancing • Cleaning • Demonstration | Coordination requirements with the CxP • A statement requiring system, subsystem, or equipment to be commissioned as a part of its parent system • A statement requiring contractor to complete construction checklists and perform tests |
must interact with the CxP. Administrative procedures for the Cx are specified in the Division 1 Section “Commissioning.”
L3.3.1 The remainder of the specification language, with the exception of Division 1 sections for temporary facilities and controls, should be mute on the subject of who must perform the work.
L3.3.2 Other Division 1 Cx Sections should describe the testing requirements for systems and assemblies.
L3.3.2.1 References in Table L-1 are to MASTERSPEC [®] section numbers and titles existing at the time this appendix was written. Refer to the current MASTERSPEC consolidated table of contents because section numbers and titles may have changed.
L3.3.3 Extent of Testing. The contractor’s involvement in Cx tests must be clearly defined. The extent of this testing is
determined by the CxP Team during the Design Phase, based on the OPR.
L3.4 Component Cx Specifications. Sections in Divisions 2 through 16 should specify testing and reporting requirements for products and equipment that are part of a system or assembly and then be referenced to the appropriate Cx sections in Division 1 for the overall system or assembly requirements.
L3.4.1 During construction, the CxP verifies that contractor activities, such as installation and start-up; testing; demonstration and training of the Owner’s O&M personnel; and Systems Manual, meet the OPR. Coordinating activities by contractor in support of the CxP should be specified within the section where the component is specified (i.e., in individual sections in Divisions 2 through 16) if special requirements are necessary. The following are examples of requirements to include in individual sections in Divisions 2 through 16.
42 ASHRAE Guideline 0-2019