L3.4.1.1 Installation and Start-Up. Include requirements for involvement of factory-authorized service representative in individual sections and for the completion of construction checklists.
L3.4.1.2 Testing. Include requirements to support the CxP in verifying test results, ranging from coordinating testing, to witnessing the test, to using contractor personnel and test equipment to verify the test report.
L3.4.1.3 Demonstration and Training. Include special requirements unique to the component within its own section.
L3.4.1.4 O&M Data. Include unique requirements for the type of information required (e.g., particular requirements about parts lists, service schedules, preventive maintenance lists, and emergency operations) for long-term maintenance of the OPR.
L3.4.2 In each section include an article under “General” that refers to Division 1 for Cx Activities for system or assembly requirements. Example:
1.XX Cx Activities
A. The roofing materials specified in this Section
are included in the Cx as a part of the building envelope system and roofing subsystem and integrated with flashing, coping, and insulation.
B. Complete the construction checklists and perform
tests specified in the Division 1 Section “Building Assemblies Commissioning Requirements.”
L4. INTRODUCTION TO GUIDE SPECIFICATIONS
This Specification Section was written in cooperation with Architectural Computer Services, Inc. (ARCOM), who are the exclusive publishers and distributors of MASTERSPEC, a product of the American Institute of Architects (AIA). MASTERSPEC Section 01 9113—General Commissioning Requirements—is included in Guideline 0 by special agreement between ASHRAE and ARCOM.
L4.1 The section includes boxed notes that are instructions to guide specifiers during editing of the specifications for a project.
L4.2 The section includes optional text in boldface font and square brackets (e.g., [ optional text ]). These optional text items include text that often occurs and provides an easy way to include these requirements in the master for consideration for each project.
L4.3 The section includes insert instructions in bold type and angle brackets (e.g., < Insert instructions >). These instructions are placed where text must be inserted and provide some guidance about the nature of the text that must be inserted. Insert instructions are used when there are an infinite number
of options that could occur, making the use of [ Optional text ] impractical.
© 2004 The American Institute of Architects (AIA) Exclusively published and distributed by Architectural Computer Services, Inc. (ARCOM) for the AIA
This MASTERSPEC Section is licensed by ARCOM for limited distribution by ASHRAE as a part of ASHRAE Guideline 0, The Commissioning Process, Appendix L, “Specifications.” The MASTERSPEC Section may be updated before Guideline 0 is updated. For information about the latest edition of this MASTERSPEC Section, contact ARCOM at (800) 424-5080.
SECTION 01 9113 GENERAL COMMISSIONING REQUIREMENTS
This Section uses the term “Architect.” Change this term to match that used to identify the design professional as defined in the General and Supplementary Conditions.
Throughout the Section, the optional text “[ each ]” is included with the term “contractor.” Retain “each” for projects that include multiple prime contractors; delete for projects that have a single prime contractor.
Verify that Section titles referenced in this Section are correct for this Project’s Specifications; Section titles may have changed.
PART 1—GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
Documents referenced in paragraph below should be prepared during schematic design phase or earlier and updated as design progresses. They should be provided to contractor when the commissioning process is implemented on Project.
B. OPR and BoD documentation are included by reference for information only.
1.2 SUMMARY
A. This Section includes general requirements that apply to implementation of the commissioning process without regard to specific systems, assemblies, and components.
B. Related Sections include the following:
List below only requirements that the reader might expect to find in this Section but are specified elsewhere. The first four and the last three subparagraphs are not yet available in MASTERSPEC but should be written and included if total building commissioning is implemented.
- Division 01 Section “Facility Substructure Commissioning” for commissioning process activities for foundations and basement systems and assemblies.