- Division 01 Section “Facility Shell Commissioning” for commissioning process activities for superstructure, exterior enclosure, and roofing systems and assemblies.
- Division 01 Section “Interiors Commissioning” for commissioning process activities for interior construction, stairways, and interior finishes systems and assemblies.
- Division 14 Section “Commissioning of Conveying Equipment” for commissioning process activities for dumbwaiters, elevators, escalators and moving walks, lifts, turntables, and scaffolding systems, assemblies, equipment, and components.
- Division 21 Section “Commissioning of Fire Suppression” for commissioning process activities for fire suppression systems, assemblies, equipment, and components.
- Division 22 Section “Commissioning of Plumbing” for commissioning process activities for plumbing systems, assemblies, equipment, and components.
- Division 23 Section “Commissioning of HVAC&R” for commissioning process activities for commissioning heating, ventilating, air-conditioning, and refrigeration systems, assemblies, equipment and components.
- Division 25 Section “Commissioning of Integrated Automation” for commissioning process activities for commissioning integrated automation systems, assemblies, equipment and components.
- Division 26 Section “Commissioning of Electrical” for commissioning process activities for electrical systems, assemblies, equipment, and components.
- Division 27 Section “Commissioning of Communications” for commissioning process activities for communication systems, assemblies, equipment, and components.
- Division 28 Section “Commissioning of Electronic Safety and Security” for commissioning process activities for electronic safety and security systems, assemblies, equipment, and components.
- Division 33 Section “Commissioning of Utilities” for commissioning process activities for water, wells, sanitary sewerage, storm drainage, fuel distribution, hydronic and steam energy, electrical, and communications utilities systems, assemblies, equipment, and components.
1.3 DEFINITIONS
Retain acronyms, abbreviations, and terms below that remain after this Section has been edited.
A. BoD: Basis of Design. A document, prepared by Architect, that records concepts, calculations, decisions, and product selections used to meet the OPR and to satisfy applicable regulatory requirements, standards, and guidelines. The document includes both narrative descriptions and lists of individual items that support the design process. B. Cx Plan: A document, prepared by CxP, that outlines the organization, schedule, allocation of resources, and documentation requirements of the commissioning process. C. CxP: Commissioning Provider.
D. OPR: Owner’s Project Requirements. A document, prepared by Owner, that details the functional requirements of Project and expectations of how it will be used and operated. This document includes Project goals, measurable performance criteria, cost considerations, benchmarks, success criteria, and supporting information. E. Systems, Assemblies, Equipment, and Components: Where these terms are used together or separately, they shall mean “as-built” systems, assemblies, equipment, and components.
1.4 COMMISSIONING TEAM
A. Members Appointed by Contractor(s): Individuals, each having authority to act on behalf of the entity he or she represents, explicitly organized to implement the commissioning process through coordinated actions. The commissioning team shall consist of, but not be limited to, representatives of [ each ]contractor, including Project superintendent and subcontractors, installers, suppliers, and specialists deemed appropriate by the CxP. B. Members Appointed by Owner:
- CxP: An entity identified by the Owner who leads, plans, schedules, and coordinates the commissioning team to implement the commissioning process. Owner will engage the CxP under a separate contract.
- Representatives of the facility user and operation and maintenance personnel.
- Architect and engineering design professionals.
1.5 OWNER’S RESPONSIBILITIES
A. Provide the OPR documentation to the CxP and
[ each ]contractor for information and use. B. Assign operation and maintenance personnel and schedule them to participate in commissioning team activities.
Coordinate activities specified in paragraph below with Owner-Architect and Architect-Consultant agreements.
C. Provide the BoD documents, prepared by Architect and approved by Owner, to the CxP and [ each ]contractor for use in developing the Cx Plan, Systems Manual, and operation and maintenance training plan.
1.6 [EACH]CONTRACTOR’S RESPONSIBILITIES
Coordinate this Article with requirements specified in Division 01 Section “Summary of Multiple Contracts” for Project Coordinator’s responsibilities.
A. [ Each ]contractor and their subcontractors shall assign representatives with expertise and authority to act on their behalf and schedule them to participate in and perform commissioning process activities including, but not limited to, the following:
- Evaluate performance deficiencies identified in test reports and, in collaboration with entity responsible