for system and equipment installation, recommend corrective action. 2. Cooperate with the CxP for resolution of issues recorded in “issues and resolution log.” 3. Attend and participate in commissioning team meetings held [ weekly ] [ biweekly ] [ monthly ] [ variable ] < Insert frequency >. 4. Integrate and coordinate commissioning process activities with construction schedule. 5. Review and accept construction checklists provided by the Cx Provider. 6. Complete [ paper ] [ electronic ] construction checklists as Work is completed and provide to the Cx Provider on a [ daily ] [ weekly ],< Insert frequency >. basis. 7. Review and accept commissioning process test procedures provided by the Cx Provider. 8. Accomplish commissioning process test procedures.
1.7 CxP’S RESPONSIBILITIES
Include CxP responsibilities in this Article that have impact on contractor activities and responsibilities.
A. Organize and lead the commissioning team. B. Provide Cx Plan.
C. Convene commissioning team meetings.
D. Provide project-specific construction checklists and commissioning process test procedures. E. Verify the execution of commissioning process activities using random sampling. The sampling rate may vary from 1 to 100 percent. Verification will include, but is not limited to, equipment submittals, construction checklists, training, operating and maintenance data, tests, and test reports to verify compliance with the OPR. When a random sample does not meet the requirement, CxP will report the failure in the “issues and resolution log.” F. Prepare and maintain issues log. G. Prepare and maintain completed construction checklist log. H. Witness systems, assemblies, equipment, and component start-up. I. Compile test data, inspection reports, and certificates and include them in the Systems Manual and commissioning process report.
PART 2—PRODUCTS (NOT USED)
PART 3—EXECUTION (NOT USED)
END OF SECTION 01 9113