LEED v5 BD+C Rating System_November 2025_clean - Page 041
Extracted Content
AND/OR
Option 2. Electric Vehicle Readiness (1 point)
Make the minimum number of total parking spaces used by the project EV ready as specified in Table 2. EV-ready parking spaces must provide a full-circuit installation, including 208–240 volts, have a 40-amp panel capacity, and a conduit (raceway) with wiring that terminates in a junction box or charging outlet.
Any space with an installed EVSE counted for credit under Option 1 may not be counted for credit as an EV-ready space under Option 2.
Table 2. Points for EV-Ready Parking (Percentage of Total Parking Spaces)
| Commercial | Residential | Points |
|---|---|---|
| At least 10% or at least 10 spaces, whichever is greater. | At least 20% or at least 20 spaces, whichever is greater. | 1 |
U.S. Green Building Council LEED v5 Reference Guide for Building Design and Construction, November 2025 Edition 34