During construction, review submittals and substitutions for design deviations that impact the OPR, attend milestone meetings at 50% and 100% completion, and perform a sample review (minimum 10%) of completed contractor documentation for quality assurance/quality control. For envelope, include testing in the commissioning documents and witness a sample of tests (not required for Core and Shell projects).
- Occupancy/operations phase: Develop an ongoing commissioning plan.