LEED v5 BD+C Rating System_November 2025_clean - Page 093

Extracted Content

Energy and Atmosphere Credit

ELECTRIFICATION

EAc1

New Construction (1–5 points): 5 points are required for LEED BD+C: New Construction Platinum projects Core and Shell (1–4 points): 4 points are required for LEED BD+C: Core and Shell Platinum projects

INTENT

To encourage building design that does not depend on burning fuel on-site, which leads to better indoor and outdoor air quality and to low-carbon operations as the grid decarbonizes.

REQUIREMENTS: NEW CONSTRUCTION

Achievement PathwaysPoints

New Construction

1–5

Option 1. No On-Site Combustion

5

OR


Option 2. No On-Site Combustion Except at Low Temperatures
1–4

Path 1. Space Heating

2

AND/OR



Path 2. Service Water Heating

1

AND/OR



Path 3. Cooking and Other Process Loads

1

Option 1. No On-Site Combustion (5 points)

Design and operate the project from start-up with no on-site combustion except for emergency support systems.

Combined weighted average equipment efficiency for space heating and service water heating (SWH) must be at least 1.8 coefficient of performance (COP).

The following equipment may be excluded from the COP determination:

- Space-heating equipment in climate zones 0–2.

- Supplemental heating equipment designed only for operation at low temperatures.

- SWH equipment in nonresidential spaces complying with the point-of-use water

heater criteria in ASHRAE 90.1-2022, Section 11.5.2.3.3, W05, without exceptions.

U.S. Green Building Council LEED v5 Reference Guide for Building Design and Construction, November 2025 Edition 86