Materials and Resources Credit
CONSTRUCTION AND DEMOLITION WASTE DIVERSION
MRc5
New Construction (1–2 points) Core and Shell (1–2 points)
INTENT
To reduce construction and demolition waste disposed of in landfills and incineration facilities and pollution to the environment. To reduce the environmental impacts and embodied carbon of manufacturing new materials and products. To delay the need for new landfill facilities that are often located in frontline communities. To create green jobs and materials markets for building construction services.
REQUIREMENTS
| Achievement Pathways | Points |
|---|---|
New Construction and Core and Shell | 1–2 |
Construction and Demolition Materials Management Plan | |
AND | |
Diversion | 1–2 |
Comply with the following requirements:
Construction and Demolition Materials Management Plan
Develop and implement a construction and demolition (C&D) materials management plan and achieve points through diversion and recycling.
AND
Diversion (1–2 points)
Follow the materials management plan and provide a final waste management report detailing all waste generated, including disposal and diversion rates for the project. Calculations can be by weight or volume but must be consistent throughout. Points are awarded according to Table 1.
Divert C&D waste materials by using strategies including off-site salvage, source-separation for single-material recycling, mixed C&D recycling, and industry/manufacturer take-back programs.
U.S. Green Building Council LEED v5 Reference Guide for Building Design and Construction, November 2025 Edition 146