leed_checklist-1 (1) - Full Extract

PDF Page 1

Open page note

LEED V4 RATING SYSTEM SELECTION GUIDANCE

PDF Page 2

Open page note

LEED V4 RATING SYSTEM SELECTION GUIDANCE

Now that you know your facility meets the minimum requirements for LEED certification, it’s time to decipher which classification you fall under. Use this guide to assist in your planning.

Source: http://www.usgbc.org/credits/existing-buildings/v4/minimum-program-requirements

LEED FOR BUILDING DESIGN AND CONSTRUCTION
Buildings that are new construction or major renovation. At least 60% of the project’s gross floor area
must be complete by the time of certification.
Source: http://www.usgbc.org/credits/existing-buildings/v4/minimum-program-requirements
Col2
BD+C: New ConstructionNew construction, high-rise residential of at least nine stories or major renovation
of some building types (see exclusions here).
BD+C: Core and ShellNew construction or major renovation for plumbing units, electrical, mechanical
and the exterior shell of a building, not an interior ft out.
BD+C: Data CentersBuildings designed for computing equipment, servers and data storage.
BD+C: Healthcare24/7 hospitals providing inpatient and long term care.
BD+C: HospitalityHospitality buildings, with long or short term lodging, in the service industry.
BD+C: RetailShowrooms, storage areas for customer service or buildings used for retail sales
of product goods.
BD+C: SchoolsBuildings on K-12 school grounds primarily consisting of learning spaces.
BD+C: Warehouses and
Distribution Centers
Storage facilities for personal or commercial goods.
BD+C: HomesResidential buildings, single or multi-family, of 1 to 3 stories.
BD+C: Multifamily MidriseMulti-family buildings with more than 50% residential space, and
between 4-8 stories.
LEED FOR INTERIOR DESIGN AND CONSTRUCTION
Interior spaces that are a complete interior ft-out. In addition, at least 60% of the project’s gross foor
area must be complete by the time of certifcation.
LEED FOR INTERIOR DESIGN AND CONSTRUCTION
Interior spaces that are a complete interior ft-out. In addition, at least 60% of the project’s gross foor
area must be complete by the time of certifcation.
ID+C: Commercial InteriorsNone retail or hospitality interior spaces.
ID+C: HospitalityInterior spaces, with long or short term lodging, in the service industry.
ID+C: RetailInterior spaces used for customer service or retail sales of product goods.

PDF Page 3

Open page note

LEED FOR OPERATIONS AND MAINTENANCE
Buildings that are fully operational and occupied for at least one year. The project may be undergoing
improvement work or little to no construction. Must include the entire building’s gross floor area in the
project.
Source http://www.usgbc.org/credits/existing-buildings/v4/minimum-program-requirements
Col2
O+M: Existing BuildingsNon K-12 educational, retail, data centers, warehouses, distribution centers, or
hospitality buildings.
O+M: Data CentersExisting buildings designed for computing equipment, servers and data storage.
O+M: HospitalityExisting hospitality facilities, with long or short term lodging, in the service
industry.
O+M: RetailExisting showrooms, storage areas for customer service or buildings used for
retail sales of product goods.
O+M: SchoolsExisting buildings made up of core and ancillary learning spaces on K-12 school
grounds. May also be used for higher education and non-academic buildings on
school campuses.
O+M: Warehouses and
Distribution Centers
Existing buildings on K-12 school grounds primarily consisting of learning spaces.
LEED FOR NEIGHBORHOOD DEVELOPMENT
New land development projects or redevelopment projects containing residential uses, nonresidential
uses, or a mix. Projects may be at any stage of the development process, from conceptual planning
through construction. It is recommended that at least 50% of total building foor area be new
construction or major renovation. Buildings within the project and features in the public realm are
evaluated.
Source: http://www.usgbc.org/credits/existing-buildings/v4/minimum-program-requirements
LEED FOR NEIGHBORHOOD DEVELOPMENT
New land development projects or redevelopment projects containing residential uses, nonresidential
uses, or a mix. Projects may be at any stage of the development process, from conceptual planning
through construction. It is recommended that at least 50% of total building foor area be new
construction or major renovation. Buildings within the project and features in the public realm are
evaluated.
Source: http://www.usgbc.org/credits/existing-buildings/v4/minimum-program-requirements
ND: PlanUnder construction or projects still within planning phases.
ND: Built ProjectFinished development projects.
CHOOSING BETWEEN RATING SYSTEMSCHOOSING BETWEEN RATING SYSTEMS
Step 1:First, assign a rating system to each square foot or square meter of your building.
Step 2:Calculate the percentage of your facility that meets each rating system.
Step 3:Choose the most appropriate rating system based on the resulting percentages.
Rule 1:Less than 40% of the gross foor area should not be used.
Rule 2:Greater than 60% of the gross foor area should be used.
Rule 3:Percentages between 40% and 60% of the gross foor area, then independently
assess each situation and decide which rating system is most applicable.