LEED v5 ID+C Addenda Table - only_02-20-2026 - Full Extract
PDF Page 1
LEED v5 Interior Design and Construction Addenda
| Page | Category and Prerequisite/Credit Name | Location | Issue | Post Date |
|---|---|---|---|---|
| 50 | LTc2: Transportation Demand Management | Requirements | See February 2026 tracked changes Rating System document for all changes to this credit. | 2/20/2026 |
| 54 | LTc2: Transportation Demand Management | Reference Guide Content | See February 2026 Reference Guide for all changes to this section. | 2/20/2026 |
| 69 | LTc3: Electric Vehicles | Requirements | ID+C Requirements, Option 2 Change the 9 to an 8 in “has an accessible parking space at least 9 feet (2.5 meters) wide” | 2/20/2026 |
| 149 | EAc1: Electrification | Requirements > Option 4 > Table 2 | In the “Base building minimum threshold” column, shift whole scale 1 point down for row-‘O+M’. (6 points —> 5 points; 5 points —> 4 points; 4 points —> 3 points; 2 points —> 1 point.) | 2/20/2026 |
| 184 | EAc3: Renewable Energy | Requirements > Renewable Energy Classifications > Tier 3 | Under Tier 3, revise second bullet to be: Renewable fuels that are Green-e® Renewable Fuels certified or equivalent. | 2/20/2026 |
| 201 | EAc4: Enhanced Commissioning | Requirements Explained > Option 1 > Timing of CxP engagement | Option 1 > Timing of CxP engagement Delete the following sentence: “If the CxP is engaged after pre-design, alternative measures must be taken to ensure alignment with the intent of the Standard 202 timeline.” and replace with the following sentence: “In certain scenarios, it may be possible for the CxP to be engaged after pre-design and still meet the intent of the ASHRAE 202 timeline.” | 2/20/2026 |
| 229 | MRp1: Planning for Zero Waste Operations | Intent Requirements | Change all (6) instances of “building” to “project” in the Intent and Requirements. | 2/20/2026 |
| 258 | MRc3: Low-Emitting Materials | Requirements > Table 1 | In Table 1. Thresholds for Low-Emitting Materials: The first row (for 1 point) should remain the same. The second row (for 2 points) should read, “>90% of all products in each product category” The third row (for 3 points) should read, “>80% of all products in each additional product category” The fourth row (for 4 points) should read, “>80% of all products in each additional product category” | 2/20/2026 |
| 258 | MRc3: Low-Emitting Materials | Requirements Requirements Explained > Calculating Product Category Achievement | Requirements: - In the first sentence, remove phrase “permanently installed products,” - Under Flooring and Insulation product category, delete all instances of “membrane” - Under Furniture product category, delete “permanently installed” from the second bullet. Requirements Explained: Delete “membrane” from the first sentence in the fourth paragraph. | 2/20/2026 |
| 262 | MRc3: Low-Emitting Materials | Requirements Explained | Revise the the last two sentences of the second paragraph to read as: “Projects targeting two or four product categories must achieve low-emitting criteria for 90% or more of all products in each product category. Projects targeting six or eight product categories must achieve low-emitting criteria for 80% or more of all products in each additional product category.” | 2/20/2026 |
Addenda LEED v5 Interior Design and Construction February 20, 2026
PDF Page 2
2
| Page | Category and Prerequisite/Credit Name | Location | Issue | Post Date |
|---|---|---|---|---|
| 276 | MRc4: Building Product Selection and Procurement | Requirements Explained > Table 1 | In the Flooring row: -Strike Terrazzo flooring from the examples of products. -Remove the ‘s’ from ‘Laminates Flooring’ example. -Remove ‘Wood and composite’ from ‘Wood and composite wood subflooring’ example. Add ‘Reused solid’ before ‘wood.’ -Remove Wall base example. In the Wall row remove the following examples: - Cubicle wall - Window treatments | 2/20/2026 |
| 339 | EQc3: Accessibility and Inclusion | Requirements Explained | Add “(ONLY FOR PROJECTS IN REGIONS WITH NO ACCESSIBILITY CODE)” after RAMPS FOR ACCESSIBLE ROUTES AND ENTRANCES, CLEAR WIDTH FOR HUMAN PASSAGE, and FRONT APPROACH WHEELCHAIR ACCESSIBLE SECTION AND Delete ” as mandated by the Americans with Disabilities Act (ADA) in the first sentence under RAMPS FOR ACCESSIBLE ROUTES AND ENTRANCES (ONLY FOR PROJECTS IN REGIONS WITH NO ACCESSIBILITY CODE) | 2/20/2026 |
| 341 | EQc3: Accessibility and Inclusion | Requirements Explained | BD+C and ID+C: Requirements Explained > Table 3. or Table 2. Change “single-use restroom OR one multi-use” to “single-user restroom OR one multi-user” in the second row. | 2/20/2026 |
| 356 | EQc5: Air Quality Testing and Monitoring | Requirements Explained > OPTION 2. CONTINUOUS INDOOR AIR MONITORING > Monitor Specifications | Under the Monitor specifications section, delete “Grade B” after “UL 2095” and change “2095” to “2905” in the last section of the last sentence. | 2/20/2026 |
*Shaded rows denote rating system changes.
Note: The online version of the rating system takes precedent over the rating system portions of the LEED v5 project guidance and application; project teams are required to adhere to the rating system and rating system
addenda effective at the time of the project’s registration date.
Addenda LEED v5 Interior Design and Construction February 20, 2026